Do Interior Works Need an Al Aryam NOC?
Yes. Interior works in Mira and Mira Oasis need the Al Aryam NOC as well, and changes involving partitions also need DDA.
The short answer
Yes, interior works in Mira and Mira Oasis also need the Al Aryam NOC. Changes that involve partitions need both the NOC and DDA. Very minor works depend on our review: we advise if DDA is needed, and they can sometimes go only through the master developer. Send us your scope of works, and we prepare what is needed, get in touch with the Al Aryam engineering team and obtain the NOC.
Mira and Mira Oasis
Mira and Mira Oasis guides
Official site: Dubai Development Authority (DDA). Structural Solutions is an independent engineering consultancy and is not part of Al Aryam, PMO or DDA.
What you need to know
- Moving walls: Partition changes need DDA as well.
- Same in both: Mira and Mira Oasis follow the same route.
- Contractors: A gate pass is needed to work on site.
- Plans: The master developer can give as-built drawings, or we obtain them on your behalf.
Documents you will need
- Scope of works
- Proposed drawings
- Owner documents
- Other documents, if the reviewing team asks for them
How it works
How it works
1. Scope
You tell us what you want to change.
2. Drawings
The master developer can give as-built drawings, or we obtain them on your behalf. We prepare the proposed drawings.
3. Al Aryam NOC
We get in touch with the Al Aryam engineering team and obtain the NOC.
4. DDA
Major works, including partition changes, go to DDA. For very minor works, we review and advise.
5. Gate pass
Your contractor gets the gate pass to work on site.
Who does what
Who is involved
Al Aryam
Its engineering team reviews the application and issues the NOC directly.
Who issues the NOC? →Dubai Development Authority (DDA)
Approves major works, including changes to partitions, after the Al Aryam NOC.
Do I need DDA? →Structural Solutions
An independent consultancy, not part of Al Aryam. We prepare the drawings, get in touch with the Al Aryam team and obtain the NOC.
Al Aryam NOC guide →What can hold up an application
- Scope of works not clear
- Proposed drawings incomplete
- Owner documents missing
- The reviewing team asks for more documents
Questions
Questions owners ask
Do I need a NOC to renovate inside?
Yes, interior works need the Al Aryam NOC.
Does moving a partition need DDA?
Yes, changes involving partitions need DDA.
What about very small works?
We review them and advise if DDA is needed.
Can I start before the NOC?
No, get the NOC first.