Mira and Mira Oasis Villa Modification NOC

Every modification in Mira and Mira Oasis needs the Al Aryam NOC. Major works, including partition changes, then need DDA. We handle both.

The short answer

Every modification to a home in Mira or Mira Oasis needs the Al Aryam NOC, including interior works. Changes involving partitions, extensions and structural work need the Al Aryam NOC and DDA. Very minor works depend on our review: we advise if DDA is needed, and they can sometimes go only through the master developer. Extensions are reviewed case by case. We prepare the scope and drawings, get in touch with the Al Aryam engineering team, and obtain the NOC.

NOCAl Aryam
Major worksDDA as well
FeeAED 2,100 or AED 3,150

Fees

Al Aryam NOC fees

Fees depend on the type of work. Al Aryam confirms the amount for your application, and DDA fees are separate.

Type of workAl Aryam NOC fee
Minor worksAED 2,100
Major worksAED 3,150

Mira and Mira Oasis

Mira and Mira Oasis guides

Official site: Dubai Development Authority (DDA). Structural Solutions is an independent engineering consultancy and is not part of Al Aryam, PMO or DDA.

What you need to know

  • Townhouses: Shared walls need careful design.
  • Plans: From the master developer, or we obtain them on your behalf.
  • Contractors: A gate pass is needed to work on site in Mira Oasis, through PMO.
  • Same route: Mira and Mira Oasis.

Documents you will need

  • Scope of works
  • Proposed drawings
  • Owner documents
  • Other documents, if the reviewing team asks for them

How it works

How it works

1. Scope

You tell us what you want to change.

2. Drawings

The master developer can give as-built drawings, or we obtain them on your behalf. We prepare the proposed drawings.

3. Al Aryam NOC

We get in touch with the Al Aryam engineering team and obtain the NOC.

4. DDA

Major works, including partition changes, go to DDA. For very minor works, we review and advise.

5. Gate pass

Your contractor gets the gate pass to work on site.

Who does what

Who is involved

🏘️

Al Aryam

Its engineering team reviews the application and issues the NOC directly.

Who issues the NOC? →
🏛️

Dubai Development Authority (DDA)

Approves major works, including changes to partitions, after the Al Aryam NOC.

Do I need DDA? →
📐

Structural Solutions

An independent consultancy, not part of Al Aryam. We prepare the drawings, get in touch with the Al Aryam team and obtain the NOC.

Al Aryam NOC guide →

What can hold up an application

  • Scope of works not clear
  • Proposed drawings incomplete
  • Owner documents missing
  • The reviewing team asks for more documents

Questions

Questions owners ask

Do I need a NOC?

Yes, for every modification.

Do I need DDA?

For major works. We advise on very minor works.

What are the NOC fees?

AED 2,100 for minor works and AED 3,150 for major works.

Is Mira Oasis different?

The route is the same.