Al Aryam NOC: how to get approval for works in Mira and Mira Oasis

The Al Aryam NOC is mandatory for any villa modification in Mira and Mira Oasis. Major works such as extensions also need the DDA permit, and in Mira Oasis 1, 2 and 3 the PMO OnePermit lets your contractor work on site. We prepare the drawings and handle every step.

The short answer

To modify a villa or townhouse in Mira or Mira Oasis, you first need the Al Aryam NOC; it is mandatory for all modification works. Submit the proposed drawings with the title deed and owner's ID. Major modifications, such as extensions and structural changes, then need the Dubai Development Authority (DDA) permit. In Mira Oasis 1, 2 and 3, the PMO OnePermit then allows the contractor to work on site and issues the gate pass.

Mandatory forAll modifications in Mira and Mira Oasis
Major worksDDA permit as well
Mira Oasis 1–3PMO OnePermit and gate pass
We prepareDrawings and structural calculations
Al Aryam NOC for villa modification in Mira and Mira Oasis

Official sources: Dubai Development Authority · PMO OnePermit portal

Structural Solutions is an independent engineering consultancy and is not part of Al Aryam, PMO or Emaar.

Al Aryam NOC: what needs it

  • Extensions: New rooms, maid room, garage conversion, balcony enclosure
  • Structural: Wall removal, new openings, slabs
  • Pools: Swimming pool in the garden
  • Exterior: Pergola, car shade, painting, landscaping
  • Interior changes: We check what your scope needs
  • Before selling: Clear any unapproved works

Documents you will need

  • Title deed and owner's passport or Emirates ID
  • Existing drawings (or an as-built survey if you have none)
  • Proposed drawings and stamped structural calculations (we prepare these)
  • Landlord's written consent, if you are a tenant

By community

Which approvals you need

Al Aryam NOC first, always.

CommunityApproval routeGuides
Mira
Al Aryam → DDA
Al Aryam NOC; the DDA permit for major works.Mira modifications
Mira DDA permit
Mira Oasis 1, 2 and 3
Al Aryam → DDA → PMO
Al Aryam NOC; the DDA permit for major works; the PMO OnePermit for the contractor.Mira Oasis modifications
PMO permit

How it works

7 steps to your Al Aryam NOC

1. Scope

What you want to change, and whether it is minor or major.

2. Existing drawings

We obtain them or survey the villa.

3. Proposed drawings

Drawings and stamped structural calculations.

4. Al Aryam NOC

We submit the request and answer any comments.

5. DDA permit

For major modifications.

6. PMO permit

In Mira Oasis 1, 2 and 3, for the contractor and gate pass.

7. Completion

Completion and sign-off of the approved works.

Why Al Aryam NOC requests get delayed

  • Drawings that do not match the villa as built
  • Missing stamped structural calculations for structural works
  • Works outside the community rules
  • Missing owner documents or landlord consent
  • Works started before the NOC

Modifying your home in Mira or Mira Oasis?

Get your Al Aryam NOC handled

Send us three things on WhatsApp:

  1. Your community (Mira or Mira Oasis) and villa number
  2. Photos of the area you want to change
  3. What you want to do

We reply with the approvals your works need, prepare the drawings and take you through Al Aryam, DDA and, in Mira Oasis, the PMO permit.

Questions

Al Aryam NOC: questions

How do I get my Al Aryam NOC?

Prepare the drawings of what you want to change, then submit the request to Al Aryam with the title deed and owner's ID. Once approved, major works also need the DDA permit. We prepare the drawings and calculations and submit for you.

Is the Al Aryam NOC mandatory?

Yes. Every modification to a villa or townhouse in Mira and Mira Oasis needs the Al Aryam NOC before works start.

What is Al Aryam?

Al Aryam issues the community NOC for modification works in Mira and Mira Oasis. Owners need it before modifying their home.

Which communities need the Al Aryam NOC?

Mira and Mira Oasis.

Do I also need a DDA permit?

For major modifications, yes. Extensions, structural changes and similar works need the Dubai Development Authority (DDA) permit after the Al Aryam NOC.

Which works count as major?

Works that change the structure or add area: extensions, maid rooms, garage conversions, balcony enclosures, wall removal and similar. We check your scope and tell you.

What is the PMO permit in Mira Oasis?

In Mira Oasis 1, 2 and 3, the PMO OnePermit allows your contractor to carry out the works on site and issues the gate pass. It comes after the Al Aryam NOC.

Do I need the PMO permit in Mira?

The PMO OnePermit currently covers Mira Oasis 1, 2 and 3. We confirm the site access requirements for your community before works start.

What documents are needed for the Al Aryam NOC?

Usually the title deed, owner's passport or Emirates ID, the proposed drawings and, for structural works, stamped structural calculations. We confirm the list for your scope.

I do not have the drawings of my villa. What now?

We obtain the existing drawings where available, or survey the villa and prepare as-built drawings.

Can a tenant apply for the Al Aryam NOC?

Yes, with the landlord's written consent first.

Can I start works with only the Al Aryam NOC?

For minor works the contractor still needs site access; in Mira Oasis that is the PMO permit. For major works the DDA permit is also needed before starting.

What happens if I modified my villa without the Al Aryam NOC?

The works need to be regularised or removed. We survey, prepare as-built drawings and apply to clear them.

Do I need the Al Aryam NOC to sell my villa?

If your home has been modified, make sure each change has its NOC, permit and completion. Unapproved works can hold up the sale.

Do you work for Al Aryam?

No. Structural Solutions is an independent engineering consultancy. We prepare the drawings and calculations and manage the Al Aryam, DDA and PMO steps for the owner.