Mira and Mira Oasis Villa Extension NOC
Extensions are possible in Mira and Mira Oasis, but each case is different. They need the Al Aryam NOC and DDA approval.
The short answer
Extensions in Mira and Mira Oasis are allowed, but each case is different and subject to submission and approval. Closing a terrace in Mira Oasis, for example, is doable and has been done before. Send us your home type and idea, and we will advise. An extension needs the Al Aryam NOC, then DDA approval.
Mira and Mira Oasis
Mira and Mira Oasis guides
Official site: Dubai Development Authority (DDA). Structural Solutions is an independent engineering consultancy and is not part of Al Aryam, PMO or DDA.
What you need to know
- Terraces: Doable, subject to approval.
- Shared walls: Designed with care on townhouses.
- Plans: From the master developer, or we obtain them on your behalf.
- Look: The design should suit the home.
Documents you will need
- Scope of works
- Proposed drawings
- Owner documents
- Other documents, if the reviewing team asks for them
How it works
How it works
1. Scope
You tell us what you want to change.
2. Drawings
The master developer can give as-built drawings, or we obtain them on your behalf. We prepare the proposed drawings.
3. Al Aryam NOC
We get in touch with the Al Aryam engineering team and obtain the NOC.
4. DDA
Major works, including partition changes, go to DDA. For very minor works, we review and advise.
5. Gate pass
Your contractor gets the gate pass to work on site.
Who does what
Who is involved
Al Aryam
Its engineering team reviews the application and issues the NOC directly.
Who issues the NOC? →Dubai Development Authority (DDA)
Approves major works, including changes to partitions, after the Al Aryam NOC.
Do I need DDA? →Structural Solutions
An independent consultancy, not part of Al Aryam. We prepare the drawings, get in touch with the Al Aryam team and obtain the NOC.
Al Aryam NOC guide →What can hold up an application
- Scope of works not clear
- Proposed drawings incomplete
- Owner documents missing
- The reviewing team asks for more documents
Questions
Questions owners ask
Can I extend my home?
Each case is different. Ask us and we will advise.
Who approves it?
Al Aryam issues the NOC, and DDA approves the works.
Is it the same in Mira Oasis?
Yes.
What is the NOC fee?
AED 3,150 for major works.