Who Approves Fit-Outs in JLT?
Four parties, always in the same order. Missing the first one is the most common reason a JLT fit-out stalls.
The short answer
Fit-outs in JLT are approved in this order: the building management or owners association NOC, DMCC fit-out approval with the drawings reviewed through Concordia, Dubai Civil Defence (DCD) where fire safety changes, and finally the Concordia inspection and Certificate of Completion (COC). Restaurants and cafés also need the DM Food Safety layout approval.
What you need to know
- Why the order matters: DMCC does not review without the building NOC, and the COC needs the approved drawings and DCD.
- Tenants: A tenant needs the landlord’s consent before the building NOC.
- Food outlets: Restaurants and cafés also need the DM Food Safety layout approval, and any layout update is re-approved.
- Structural works: Mezzanines, slab openings and heavy equipment need stamped structural calculations.
Documents you will need
- Trade licence and lease, or title deed for owners
- Building management or owners association NOC
- Existing or as-built drawings of the unit
- Fit-out drawings, with stamped structural calculations where structure is affected
- Fire safety drawings where Civil Defence is involved
Who does what
The JLT approval order
We confirm the route for your tower and unit.
| Step | Approval route | Guides |
|---|---|---|
| 1. Building management Building NOC | Approves the works in the tower. | Building NOC first |
| 2. DMCC via Concordia Fit-out approval | Concordia reviews the drawings for DMCC. | DMCC fit-out approval |
| 3. Civil Defence Fire safety | Where fire safety changes. | DCD in JLT |
| 4. Concordia Inspection and COC | After the works are finished. | Concordia COC |
How it works
How we get your JLT approval
1. Unit review
Tower, unit, current layout and the works planned.
2. Existing drawings
From building management or DMCC. If the unit was changed, we survey it and update the as-built drawings.
3. Drawings and calculations
Fit-out drawings, fire safety drawings and stamped structural calculations where needed.
4. Building NOC
Building management or owners association NOC for the works.
5. DMCC via Concordia, then DCD
Concordia reviews the drawings for the DMCC approval; Civil Defence approves fire safety.
6. Inspection and COC
Concordia inspects the finished works and issues the Certificate of Completion.
Who does what
Who approves works in JLT
DMCC and Concordia
DMCC approves the fit-out. Concordia, appointed by DMCC, reviews the drawings, inspects the works and issues the COC.
Concordia vs DMCC →Dubai Civil Defence
Approves and inspects fire safety changes such as sprinklers, fire alarm and exits.
DCD in JLT →What we prepare in JLT
Why Concordia sends drawings back
- Building management NOC missing
- Drawings that do not match the unit as it stands
- Fire safety changes without DCD approval
- Structural changes without stamped calculations
- Works started before approval
Questions
Questions about JLT fit-out approval
Is JLT under Dubai Municipality?
No. Fit-outs in JLT are approved by DMCC, with the drawings reviewed through Concordia.
Can a tenant apply for a fit-out?
Yes, with the landlord’s consent and the building management NOC.
Does every fit-out need DCD?
Only where fire safety changes, such as sprinklers, fire alarm, exits or ceilings that affect them.
When can the unit open?
After Concordia inspects the works and issues the COC.