What Is Concordia in JLT?
Concordia manages the JLT towers for DMCC. For any fit-out or modification, it reviews your drawings, controls the works and issues the Certificate of Completion at the end.
The short answer
Concordia is the building and facilities management company for the JLT towers, appointed by DMCC. For fit-outs and modifications, it reviews the drawings as part of the DMCC fit-out approval, controls the works in the building, inspects the finished works and issues the Certificate of Completion (COC). Uptown Dubai and Almas Tower also go through Concordia.
What you need to know
- Drawing review: Fit-out and modification drawings are reviewed through Concordia for the DMCC approval.
- Works on site: Contractor works in the towers are controlled by Concordia.
- Inspection: Concordia inspects the finished works against the approved drawings.
- Certificate of Completion: Issued after a passed inspection and needed before the unit opens or is handed over.
Documents you will need
- Trade licence and lease, or title deed for owners
- Building management or owners association NOC
- Existing or as-built drawings of the unit
- Fit-out drawings, with stamped structural calculations where structure is affected
- Fire safety drawings where Civil Defence is involved
Who does what
Where Concordia fits
We confirm the route for your tower and unit.
| Step | Approval route | Guides |
|---|---|---|
| Building management Building NOC | NOC for the works in the tower. | Building NOC |
| DMCC Fit-out approval | Approves the fit-out. | DMCC fit-out approval |
| Concordia Review, inspection, COC | Reviews the drawings for DMCC, inspects and issues the COC. | Concordia COC |
| Civil Defence Fire safety | Approves fire safety changes. | DCD in JLT |
How it works
How we get your JLT approval
1. Unit review
Tower, unit, current layout and the works planned.
2. Existing drawings
From building management or DMCC. If the unit was changed, we survey it and update the as-built drawings.
3. Drawings and calculations
Fit-out drawings, fire safety drawings and stamped structural calculations where needed.
4. Building NOC
Building management or owners association NOC for the works.
5. DMCC via Concordia, then DCD
Concordia reviews the drawings for the DMCC approval; Civil Defence approves fire safety.
6. Inspection and COC
Concordia inspects the finished works and issues the Certificate of Completion.
Who does what
Who approves works in JLT
DMCC and Concordia
DMCC approves the fit-out. Concordia, appointed by DMCC, reviews the drawings, inspects the works and issues the COC.
Concordia vs DMCC →Dubai Civil Defence
Approves and inspects fire safety changes such as sprinklers, fire alarm and exits.
DCD in JLT →What we prepare in JLT
Why Concordia sends drawings back
- Building management NOC missing
- Drawings that do not match the unit as it stands
- Fire safety changes without DCD approval
- Structural changes without stamped calculations
- Works started before approval
Questions
Questions about Concordia
Is Concordia a government authority?
No. It is the building and facilities management for the JLT towers, appointed by DMCC. DMCC is the authority that approves the fit-out.
Do I apply to Concordia or to DMCC?
The fit-out approval is a DMCC approval, with the drawings reviewed through Concordia. The building management NOC comes first.
Which towers go through Concordia?
The JLT towers, including Uptown Dubai and Almas Tower.
Does Concordia inspect the works?
Yes. It inspects the finished works and issues the COC when they match the approved drawings.