Fit-Out Without Approval in JLT: Can Works Already Done Be Approved?
Works done without approval can stop your COC, and DMCC can stop the fit-out. Many works can be approved afterwards, with as-built drawings.
The short answer
Works carried out without approval in JLT can lead to the fit-out being stopped and the COC being refused. In many cases the works can be approved afterwards: the unit is surveyed, as-built drawings are prepared, and the works go through the building management NOC, DMCC approval via Concordia and Civil Defence. Works that cannot be approved must be changed or removed. If DMCC has stopped your fit-out, the works stay stopped until the approvals are in place.
What you need to know
- Survey: The unit as it is now.
- As-built drawings: Show the works done.
- Approvals: Building NOC, DMCC via Concordia, DCD.
- Not approvable: Changed or removed.
- Stopped fit-out: Resumes after the approvals.
Documents you will need
- Lease or title deed, and trade licence for businesses
- Building management or owners association NOC
- Existing or as-built drawings of the unit
- Proposed fit-out drawings, stamped by the consultant
- Fire safety drawings for Civil Defence
- Contractor registration with Concordia
By type of unit
Approvals by type of unit
We confirm the route for your unit.
| Unit | Approval route | Guides |
|---|---|---|
| Office Building NOC, DMCC via Concordia, DCD | Layout, MEP and fire safety. | DMCC fit-out |
| Shop Building NOC, DMCC via Concordia, DCD | Shopfront and signage too. | Shops |
| Restaurant or café Plus DM Food Safety | Kitchen layout. | Restaurants |
| Clinic Plus DHA | Health facility approval. | Clinics |
| Apartment Building or OA NOC, DMCC via Concordia | Renovation works. | Apartments |
How it works
How we get your JLT approval
1. Review
The unit, the changes and the drawings you have.
2. Drawings
Existing drawings from building management or DMCC, or we survey and redraw.
3. Building NOC
From building management or the owners association.
4. DMCC and Concordia
Fit-out approval, reviewed through Concordia.
5. Civil Defence
Fire safety drawings approved.
6. Works
By a contractor registered with Concordia.
7. COC
Concordia inspection and Certificate of Completion.
Who does what
Who approves it in JLT
Building management
The building management or owners association NOC comes first.
Building NOC first →DMCC through Concordia
DMCC approves the fit-out; Concordia reviews the drawings, inspects the works and issues the COC.
Concordia and DMCC →Structural Solutions
Prepares the drawings and calculations and handles the submissions.
Talk to our engineers →What we prepare
Why JLT submissions get returned
- Drawings that do not match the unit
- Building management NOC missing
- Fire safety changes without DCD approval
- Contractor not registered with Concordia
- Works started before approval
Questions
Questions tenants and owners ask
What happens if I fit out without approval in JLT?
The works can be stopped and the COC refused.
Can works already done be approved?
Often yes, with as-built drawings and the normal approvals.
DMCC stopped my fit-out: what now?
Get the approvals in place before the works continue.