Fit-Out Without Approval in JLT: Can Works Already Done Be Approved?

Works done without approval can stop your COC, and DMCC can stop the fit-out. Many works can be approved afterwards, with as-built drawings.

The short answer

Works carried out without approval in JLT can lead to the fit-out being stopped and the COC being refused. In many cases the works can be approved afterwards: the unit is surveyed, as-built drawings are prepared, and the works go through the building management NOC, DMCC approval via Concordia and Civil Defence. Works that cannot be approved must be changed or removed. If DMCC has stopped your fit-out, the works stay stopped until the approvals are in place.

RiskWorks stopped, no COC
Often possibleApproval afterwards
Based onAs-built drawings

What you need to know

  • Survey: The unit as it is now.
  • As-built drawings: Show the works done.
  • Approvals: Building NOC, DMCC via Concordia, DCD.
  • Not approvable: Changed or removed.
  • Stopped fit-out: Resumes after the approvals.

Documents you will need

  • Lease or title deed, and trade licence for businesses
  • Building management or owners association NOC
  • Existing or as-built drawings of the unit
  • Proposed fit-out drawings, stamped by the consultant
  • Fire safety drawings for Civil Defence
  • Contractor registration with Concordia

By type of unit

Approvals by type of unit

We confirm the route for your unit.

UnitApproval routeGuides
Office
Building NOC, DMCC via Concordia, DCD
Layout, MEP and fire safety.DMCC fit-out
Shop
Building NOC, DMCC via Concordia, DCD
Shopfront and signage too.Shops
Restaurant or café
Plus DM Food Safety
Kitchen layout.Restaurants
Clinic
Plus DHA
Health facility approval.Clinics
Apartment
Building or OA NOC, DMCC via Concordia
Renovation works.Apartments

How it works

How we get your JLT approval

1. Review

The unit, the changes and the drawings you have.

2. Drawings

Existing drawings from building management or DMCC, or we survey and redraw.

3. Building NOC

From building management or the owners association.

4. DMCC and Concordia

Fit-out approval, reviewed through Concordia.

5. Civil Defence

Fire safety drawings approved.

6. Works

By a contractor registered with Concordia.

7. COC

Concordia inspection and Certificate of Completion.

Who does what

Who approves it in JLT

🏢

Building management

The building management or owners association NOC comes first.

Building NOC first →
🏛️

DMCC through Concordia

DMCC approves the fit-out; Concordia reviews the drawings, inspects the works and issues the COC.

Concordia and DMCC →
🚒

Dubai Civil Defence

Approves the fire safety drawings for the fit-out.

DCD in JLT →
📐

Structural Solutions

Prepares the drawings and calculations and handles the submissions.

Talk to our engineers →

Why JLT submissions get returned

  • Drawings that do not match the unit
  • Building management NOC missing
  • Fire safety changes without DCD approval
  • Contractor not registered with Concordia
  • Works started before approval

Questions

Questions tenants and owners ask

What happens if I fit out without approval in JLT?

The works can be stopped and the COC refused.

Can works already done be approved?

Often yes, with as-built drawings and the normal approvals.

DMCC stopped my fit-out: what now?

Get the approvals in place before the works continue.