Do I Need Civil Defence (DCD) Approval for a JLT Fit-Out?

Yes. JLT fit-outs need Civil Defence approval for the fire safety, after the building NOC and the DMCC approval through Concordia.

The short answer

Yes. A fit-out in JLT goes through the building management NOC, the DMCC approval reviewed through Concordia, and Dubai Civil Defence (DCD) approval for the fire safety. Changes to the ceiling, sprinklers, smoke detectors, alarm, emergency lighting or exits are shown on the fire safety drawings. If DCD sends comments or rejects the drawings, they are revised and resubmitted before the works continue.

AnswerYes
CoversCeilings, sprinklers, alarm, exits
ThenConcordia COC

What you need to know

  • Ceilings: A new ceiling changes the sprinkler and detector layout.
  • Sprinklers: Moved or added heads are shown on the drawings.
  • Exits: Partitions must keep the escape routes.
  • DCD comments: Answered on revised drawings and resubmitted.
  • Rejected?: The drawings are corrected; works wait for the approval.

Documents you will need

  • Lease or title deed, and trade licence for businesses
  • Building management or owners association NOC
  • Existing or as-built drawings of the unit
  • Proposed fit-out drawings, stamped by the consultant
  • Fire safety drawings for Civil Defence
  • Contractor registration with Concordia

By type of unit

Approvals by type of unit

We confirm the route for your unit.

UnitApproval routeGuides
Office
Building NOC, DMCC via Concordia, DCD
Layout, MEP and fire safety.DMCC fit-out
Shop
Building NOC, DMCC via Concordia, DCD
Shopfront and signage too.Shops
Restaurant or café
Plus DM Food Safety
Kitchen layout.Restaurants
Clinic
Plus DHA
Health facility approval.Clinics
Apartment
Building or OA NOC, DMCC via Concordia
Renovation works.Apartments

How it works

How we get your JLT approval

1. Review

The unit, the changes and the drawings you have.

2. Drawings

Existing drawings from building management or DMCC, or we survey and redraw.

3. Building NOC

From building management or the owners association.

4. DMCC and Concordia

Fit-out approval, reviewed through Concordia.

5. Civil Defence

Fire safety drawings approved.

6. Works

By a contractor registered with Concordia.

7. COC

Concordia inspection and Certificate of Completion.

Who does what

Who approves it in JLT

🏢

Building management

The building management or owners association NOC comes first.

Building NOC first →
🏛️

DMCC through Concordia

DMCC approves the fit-out; Concordia reviews the drawings, inspects the works and issues the COC.

Concordia and DMCC →
🚒

Dubai Civil Defence

Approves the fire safety drawings for the fit-out.

DCD in JLT →
📐

Structural Solutions

Prepares the drawings and calculations and handles the submissions.

Talk to our engineers →

What we prepare

  • Fire safety drawings
  • DCD submission and comments

Why JLT submissions get returned

  • Drawings that do not match the unit
  • Building management NOC missing
  • Fire safety changes without DCD approval
  • Contractor not registered with Concordia
  • Works started before approval

Questions

Questions tenants and owners ask

Does a JLT fit-out need DCD approval?

Yes.

Do I need DCD approval to change my ceiling or sprinklers?

Yes, they are part of the fire safety drawings.

What if DCD rejects my fit-out?

The drawings are corrected and resubmitted before the works continue.

Is DCD before or after DMCC?

After the building NOC and the DMCC approval through Concordia.