Do I Need a New COC After Modifying My JLT Unit?

Yes. Modifications are fit-out works: they go through the approvals and finish with a new Concordia inspection and COC.

The short answer

Yes. Modifying a unit in JLT, for example new partitions, a new layout or MEP changes, is a fit-out: it needs the building management NOC, DMCC approval reviewed through Concordia and Civil Defence, and finishes with a Concordia inspection and a new Certificate of Completion. Updated as-built drawings show the unit after the changes.

AnswerYes
Ends withNew Concordia COC
DrawingsUpdated as-built

What you need to know

  • Approvals: Same route as a fit-out.
  • As-built: Updated after the works.
  • End of lease: The unit may need to be returned to its approved state.

Documents you will need

  • Lease or title deed, and trade licence for businesses
  • Building management or owners association NOC
  • Existing or as-built drawings of the unit
  • Proposed fit-out drawings, stamped by the consultant
  • Fire safety drawings for Civil Defence
  • Contractor registration with Concordia

By type of unit

Approvals by type of unit

We confirm the route for your unit.

UnitApproval routeGuides
Office
Building NOC, DMCC via Concordia, DCD
Layout, MEP and fire safety.DMCC fit-out
Shop
Building NOC, DMCC via Concordia, DCD
Shopfront and signage too.Shops
Restaurant or café
Plus DM Food Safety
Kitchen layout.Restaurants
Clinic
Plus DHA
Health facility approval.Clinics
Apartment
Building or OA NOC, DMCC via Concordia
Renovation works.Apartments

How it works

How we get your JLT approval

1. Review

The unit, the changes and the drawings you have.

2. Drawings

Existing drawings from building management or DMCC, or we survey and redraw.

3. Building NOC

From building management or the owners association.

4. DMCC and Concordia

Fit-out approval, reviewed through Concordia.

5. Civil Defence

Fire safety drawings approved.

6. Works

By a contractor registered with Concordia.

7. COC

Concordia inspection and Certificate of Completion.

Who does what

Who approves it in JLT

🏢

Building management

The building management or owners association NOC comes first.

Building NOC first →
🏛️

DMCC through Concordia

DMCC approves the fit-out; Concordia reviews the drawings, inspects the works and issues the COC.

Concordia and DMCC →
🚒

Dubai Civil Defence

Approves the fire safety drawings for the fit-out.

DCD in JLT →
📐

Structural Solutions

Prepares the drawings and calculations and handles the submissions.

Talk to our engineers →

Why JLT submissions get returned

  • Drawings that do not match the unit
  • Building management NOC missing
  • Fire safety changes without DCD approval
  • Contractor not registered with Concordia
  • Works started before approval

Questions

Questions tenants and owners ask

Do I need a new COC after changes?

Yes, after the inspection of the modified unit.

Do I need new as-built drawings?

Yes, showing the unit after the changes.

Is the route the same as a fit-out?

Yes.