Mezzanine or Racking: Which Approval Do I Need?
A mezzanine is a new floor and counts as floor area. Racking is storage. The approvals differ, and racking on a mezzanine needs both checked.
A mezzanine is an added floor that counts as GFA. It needs the landlord or developer NOC, the permit from the authority for the area with stamped calculations, the approved steel contractor stamp and Civil Defence approval. Racking is storage: it changes the loads on the slab and the fire safety, so it is checked for its loads and DCD approves the storage layout; whether the area authority also issues a permit depends on the area and the racking, and we confirm it for your warehouse. Racking on a mezzanine is checked and approved with the mezzanine.
What you need to know
- Mezzanine: A floor people walk on.
- Racking: Storage shelving and pallet racking.
- Both: Loads and fire safety change.
- We confirm: The route for your area and racking.
Documents you will need
- Trade licence and tenancy contract, or title deed for owners
- Landlord, building management or master developer NOC
- Existing or as-built drawings of the unit or villa
- Mezzanine drawings with stamped structural calculations
- Fire safety drawings for Civil Defence
By situation
Which route
We confirm the route for your building and area.
| Your plan | Approval route | Guides |
|---|---|---|
| Mezzanine Full mezzanine route | NOC, authority, steel stamp, DCD. | Mezzanine NOC |
| Racking only Load check and DCD | Authority by area. | — |
| Racking on a mezzanine Checked together | With the mezzanine. | JAFZA racking DSO |
How it works
How we get your mezzanine approved
1. Site and slab review
The unit, the existing slab and columns, and what the mezzanine is for.
2. Existing drawings
From the landlord, developer or authority; if missing or out of date, we survey and draw as built.
3. Design and calculations
Mezzanine drawings, steel design and stamped structural calculations, with the added floor area shown.
4. NOC
Landlord, building management or master developer NOC.
5. Permit and Civil Defence
The authority for the area approves the structure; the approved steel contractor stamps the steel; DCD approves fire safety.
6. Build, inspect, complete
The mezzanine is built as approved, inspected, and the completion certificate is issued.
Who does what
Who approves a mezzanine
Landlord or developer
Gives the NOC for the mezzanine. It comes first.
Authority for the area
Dubai Municipality, DDA, Trakhees, DSO Authority, Dubai South Authority or DMCC approves the structure with stamped calculations.
Who approves? →Approved steel contractor
A steel mezzanine needs the stamp of an approved steel contractor (also called a steel specialist).
Steel contractor stamp →Dubai Civil Defence
Every mezzanine needs DCD approval for fire safety and escape.
Civil Defence and mezzanines →What we prepare
- Load checks and stamped calculations
- Submissions
Why mezzanine submissions get returned
- Mezzanine built before approval
- No landlord or developer NOC
- Drawings that do not match the unit as built
- Slab and columns not checked for the new loads
- Steel without the approved steel contractor stamp
- Added floor area not shown
- No Civil Defence fire safety drawings
Questions
Questions owners and tenants ask
Is racking the same as a mezzanine?
No. A mezzanine is a floor; racking is storage.
Does racking need Civil Defence approval?
DCD approves the storage layout and fire safety.
Can I put racking on my mezzanine?
Only after the mezzanine and slab are checked for it.