Mezzanine and Racking Approval in Dubai Silicon Oasis (DSO)

Mezzanines and racking in DSO are approved by the DSO Authority after the landlord or building NOC, with Civil Defence.

The short answer

In Dubai Silicon Oasis, a mezzanine or racking system needs the landlord or building management NOC, stamped structural calculations, the approved steel contractor stamp for the steel, the DSO Authority permit and Dubai Civil Defence approval. A mezzanine counts as added floor area. There is no separate developer NOC in DSO.

FirstLandlord or building NOC
AuthorityDSO Authority
AlsoSteel stamp and DCD

What you need to know

  • NOC: Landlord or building management.
  • DSO Authority: Approves the works.
  • Steel: Approved steel contractor stamp.
  • DCD: Every mezzanine.

Documents you will need

  • Trade licence and tenancy contract, or title deed for owners
  • Landlord, building management or master developer NOC
  • Existing or as-built drawings of the unit or villa
  • Mezzanine drawings with stamped structural calculations
  • Fire safety drawings for Civil Defence

By situation

Your project

We confirm the route for your building and area.

SituationApproval routeGuides
Mezzanine
DSO Authority and DCD
Adds floor area.—
Racking
DSO Authority and DCD
Storage layout changes.—

How it works

How we get your mezzanine approved

1. Site and slab review

The unit, the existing slab and columns, and what the mezzanine is for.

2. Existing drawings

From the landlord, developer or authority; if missing or out of date, we survey and draw as built.

3. Design and calculations

Mezzanine drawings, steel design and stamped structural calculations, with the added floor area shown.

4. NOC

Landlord, building management or master developer NOC.

5. Permit and Civil Defence

The authority for the area approves the structure; the approved steel contractor stamps the steel; DCD approves fire safety.

6. Build, inspect, complete

The mezzanine is built as approved, inspected, and the completion certificate is issued.

Who does what

Who approves a mezzanine

🏢

Landlord or developer

Gives the NOC for the mezzanine. It comes first.

🏛️

Authority for the area

Dubai Municipality, DDA, Trakhees, DSO Authority, Dubai South Authority or DMCC approves the structure with stamped calculations.

Who approves? →
🔩

Approved steel contractor

A steel mezzanine needs the stamp of an approved steel contractor (also called a steel specialist).

Steel contractor stamp →
🚒

Dubai Civil Defence

Every mezzanine needs DCD approval for fire safety and escape.

What we prepare

Why mezzanine submissions get returned

  • Mezzanine built before approval
  • No landlord or developer NOC
  • Drawings that do not match the unit as built
  • Slab and columns not checked for the new loads
  • Steel without the approved steel contractor stamp
  • Added floor area not shown
  • No Civil Defence fire safety drawings

Questions

Questions owners and tenants ask

Who approves a mezzanine in DSO?

The DSO Authority, after the landlord or building NOC, with Civil Defence.

Is there a developer NOC in DSO?

No separate developer NOC.