Mezzanine Built Without Approval in a Dubai Warehouse: Retrospective Approval
A mezzanine must be approved before it is built. If yours was built without a permit, it needs a retrospective approval.
The short answer
A mezzanine in Dubai must be approved before construction. If it was already built without a permit, a retrospective approval is needed: the mezzanine is surveyed and drawn as built, its structure and the slab are assessed, strengthening is designed where needed, and the landlord NOC, the authority for the area, the approved steel contractor stamp and Dubai Civil Defence follow, as for a new mezzanine. Unapproved mezzanines can come up at lease renewal, sale, change of use or inspection.
What you need to know
- Survey: The mezzanine is measured and drawn as built.
- Assessment: Steel, connections, slab and footings are checked.
- Strengthening: Designed where the structure falls short.
- Approvals: Landlord NOC, authority for the area, steel contractor stamp and DCD.
- When it comes up: Lease renewal, sale, change of use, inspections.
Documents you will need
- Trade licence and tenancy contract, or title deed for owners
- Landlord, building management or master developer NOC
- Existing or as-built drawings of the unit or villa
- Mezzanine drawings with stamped structural calculations
- Fire safety drawings for Civil Defence
By situation
Your situation
We confirm the route for your building and area.
| Situation | Approval route | Guides |
|---|---|---|
| Built, no drawings Survey and as-built drawings | Then assessment. | — |
| Built, structure unknown Structural assessment | Strengthening if needed. | Calculations |
| JAFZA Trakhees CED | Retrospective route. | JAFZA |
| DIP PID/DIP NOC, then DM | Retrospective route. | DIP |
How it works
How we get your mezzanine approved
1. Site and slab review
The unit, the existing slab and columns, and what the mezzanine is for.
2. Existing drawings
From the landlord, developer or authority; if missing or out of date, we survey and draw as built.
3. Design and calculations
Mezzanine drawings, steel design and stamped structural calculations, with the added floor area shown.
4. NOC
Landlord, building management or master developer NOC.
5. Permit and Civil Defence
The authority for the area approves the structure; the approved steel contractor stamps the steel; DCD approves fire safety.
6. Build, inspect, complete
The mezzanine is built as approved, inspected, and the completion certificate is issued.
Who does what
Who approves a mezzanine
Landlord or developer
Gives the NOC for the mezzanine. It comes first.
Authority for the area
Dubai Municipality, DDA, Trakhees, DSO Authority, Dubai South Authority or DMCC approves the structure with stamped calculations.
Who approves? →Approved steel contractor
A steel mezzanine needs the stamp of an approved steel contractor (also called a steel specialist).
Steel contractor stamp →Dubai Civil Defence
Every mezzanine needs DCD approval for fire safety and escape.
What we prepare
- Survey and as-built drawings
- Structural assessment and strengthening design
- Retrospective approval submissions
Why mezzanine submissions get returned
- Mezzanine built before approval
- No landlord or developer NOC
- Drawings that do not match the unit as built
- Slab and columns not checked for the new loads
- Steel without the approved steel contractor stamp
- Added floor area not shown
- No Civil Defence fire safety drawings
Questions
Questions owners and tenants ask
Can a mezzanine be approved after it is built?
It needs a retrospective approval, with a survey, assessment and the same approvals as a new one.
Is it enough to submit calculations?
No. The full approval route applies, including Civil Defence.
Can it be refused?
The authority decides; strengthening or changes may be needed.
What should I do first?
Get it surveyed and assessed.