How Do I Get an Al Aryam NOC?
To get an Al Aryam NOC, prepare your scope of works, proposed drawings and owner documents. We get in touch with the Al Aryam engineering team and obtain the NOC.
To get an Al Aryam NOC for a home in Mira or Mira Oasis, the application goes to the Al Aryam engineering team with the scope of works, the proposed drawings and the owner documents. Al Aryam issues the NOC directly, and its team may ask for other documents depending on the application. We prepare the drawings, get in touch with the team and obtain the NOC for you. Changes involving partitions, extensions and structural work need the Al Aryam NOC and DDA. Very minor works depend on our review: we advise if DDA is needed, and they can sometimes go only through the master developer.
Fees
Al Aryam NOC fees
Fees depend on the type of work. Al Aryam confirms the amount for your application, and DDA fees are separate.
| Type of work | Al Aryam NOC fee |
|---|---|
| Minor works | AED 2,100 |
| Major works | AED 3,150 |
Mira Oasis
Mira and Mira Oasis guides
Official site: Dubai Development Authority (DDA). Structural Solutions is an independent engineering consultancy and is not part of Al Aryam, PMO or DDA.
What you need to know
- All modifications: The NOC is needed for every modification, including interior works.
- Drawings: The master developer can give as-built drawings, or we obtain them on your behalf.
- Extra documents: These depend on the team reviewing the application.
- Contractors: A gate pass is needed to work on site.
Documents you will need
- Scope of works
- Proposed drawings
- Owner documents
- Other documents, if the reviewing team asks for them
How it works
How it works
1. Scope
You tell us what you want to change.
2. Drawings
We obtain the as-built drawings from the master developer, or on your behalf, and prepare the proposed drawings.
3. Al Aryam NOC
We get in touch with the Al Aryam engineering team and obtain the NOC.
4. DDA
Major works, including partition changes, go to DDA. For very minor works, we review and advise.
5. Gate pass
Your contractor gets the gate pass to work on site.
Who does what
Who is involved
Al Aryam
Its engineering team reviews the application and issues the NOC directly.
Al Aryam NOC guide →Dubai Development Authority (DDA)
Issues the permit for major works, after the Al Aryam NOC.
Is Al Aryam under DDA? →Structural Solutions
An independent consultancy, not part of Al Aryam. We prepare the drawings, get in touch with the Al Aryam team and obtain the NOC.
Al Aryam NOC guide →What we handle
- Al Aryam NOC
- Mira and Mira Oasis modifications
- PMO gate pass
What can hold up an application
- Scope of works not clear
- Proposed drawings incomplete
- Owner documents missing
- The reviewing team asks for more documents
Questions
Questions owners ask
How do I apply for an Al Aryam NOC?
Send us your scope and we handle it. We get in touch with the Al Aryam engineering team and obtain the NOC.
Who issues it?
Al Aryam issues it directly.
Is the process the same in Mira and Mira Oasis?
Yes, it is the same in both.
What happens after the NOC?
Major works, including partition changes, go to DDA. For very minor works, we review and advise.
Related guides

