DSO Fit-Out Completion Certificate and the DCD Final Inspection
After the works, the unit is inspected, including the Civil Defence final inspection, and the completion is issued before the unit opens.
At the end of a fit-out in Dubai Silicon Oasis, the works are inspected against the approved drawings, including the Civil Defence (DCD) final inspection of the fire safety systems, and the completion is issued before the unit opens. If anything on site differs from the approved drawings, updated as-built drawings are prepared and approved first. If the inspection fails, the comments are fixed and the inspection is booked again.
What you need to know
- Approved drawings: The works are inspected against them.
- DCD final inspection: Sprinklers, alarm, exits and emergency lighting.
- Site changes: Shown on updated as-built drawings first.
- Failed inspection: Fix the comments and book again.
- Opening: Only after completion.
Documents you will need
- Lease or title deed, and trade licence for businesses
- Building management or landlord NOC
- Existing or as-built drawings of the unit
- Proposed fit-out drawings, stamped by the consultant
- Fire safety drawings for Civil Defence
- Structural calculations where loads or openings change
By type of unit
Approvals by type of unit in DSO
We confirm the route for your unit.
| Unit | Approval route | Guides |
|---|---|---|
| Office Building NOC, DSO Authority, DCD | Layout, MEP and fire safety. | Offices |
| Retail shop Building NOC, DSO Authority, DCD | Shop front and signage too. | Shops |
| Restaurant or cafe Plus DM Food Safety | Kitchen layout, LPG or electric cooking. | Restaurants |
| Clinic Plus DHA | Health facility approval. | Clinics |
| Warehouse or industrial Building NOC, DSO Authority, DCD | Racking, mezzanines, floor loads. | Warehouses |
How it works
How we get your DSO approval
1. Review
The unit, the planned works and the drawings you have.
2. Drawings
Existing drawings, or we survey and redraw the unit.
3. Building NOC
From building management or the landlord.
4. DSO Authority
Fit-out or building permit, part of DIEZ.
5. Civil Defence
Fire safety drawings approved.
6. Works
Carried out to the approved drawings.
7. Completion
Inspection and completion before the unit opens.
Who does what
Who approves it in Dubai Silicon Oasis
Building management or landlord
Issues the NOC for the works in your unit. There is no developer NOC in DSO.
Building NOC →DSO Authority (DIEZ)
Issues the fit-out or building permit for works in Dubai Silicon Oasis.
DIEZ approval →Dubai Civil Defence
Approves the fire safety for every commercial fit-out change and inspects before completion.
DSO and DCD →Structural Solutions
Prepares the drawings and calculations and handles the submissions as consultant.
Talk to our engineers →What we prepare
- As-built drawings
- Inspection coordination
- Failed inspection help
Why DSO submissions get returned
- Building management or landlord NOC missing
- Drawings that do not match the unit on site
- Fire safety changes not shown for Civil Defence
- Structural changes without stamped calculations
- Works started before the permit
DSO BCC
DSO fit-out completion certificate (BCC) stuck?
The completion certificate is also called the BCC (Building Completion Certificate), and many owners simply call it sign-off.
In Dubai Silicon Oasis the fit-out is closed by the DSO Authority, with the Civil Defence (DCD) final inspection where fire and life safety works are included.
- Fit-out completion certificate
- Civil Defence (DCD) completion pending
- Works don’t match the approved drawings
- My contractor can’t get the completion certificate
Contact our engineering team on WhatsApp or call us directly on +971 55 339 4451.
Questions
Questions tenants and owners ask
Is the DSO fit-out completion certificate the same as the BCC?
The completion certificate is also called the BCC (Building Completion Certificate), and many owners simply call it sign-off.
Can I open before the DCD inspection?
No, the unit opens after the inspection and completion.
What if the inspection fails?
Fix the comments and book the inspection again.
What if the works changed on site?
Updated as-built drawings are approved first.
Who books the inspections?
The consultant or contractor; we coordinate them.