DSO Restaurant and Cafe Fit-Out Approval: Food Safety, LPG and Civil Defence
A restaurant or cafe in Dubai Silicon Oasis needs the building NOC, the DSO Authority (DIEZ) permit, Civil Defence and the Dubai Municipality Food Safety layout approval.
The short answer
A restaurant or cafe fit-out in Dubai Silicon Oasis goes through four approvals: the building management or landlord NOC, the DSO Authority permit for the works, Dubai Civil Defence for the fire safety and the kitchen fire suppression, and the Dubai Municipality (DM) Food Safety approval of the kitchen and food layout. Any later change to the kitchen or layout needs the layout approved again. For gas cooking, the approved LPG provider gives its own approval; a kitchen that cooks only with electricity gives an undertaking letter instead.
What you need to know
- Kitchen layout: Equipment, flow, storage and washing areas, approved by DM Food Safety.
- Any update: A change to the kitchen or layout is approved again.
- LPG: The approved LPG provider gives its own approval for the gas system.
- Electric cooking: An undertaking letter instead of the LPG approval.
- Hood and suppression: Kitchen fire suppression is approved by Civil Defence.
- Exhaust: Hood and duct routes shown on the drawings.
Documents you will need
- Lease or title deed, and trade licence for businesses
- Building management or landlord NOC
- Existing or as-built drawings of the unit
- Proposed fit-out drawings, stamped by the consultant
- Fire safety drawings for Civil Defence
- Structural calculations where loads or openings change
By type of unit
Restaurant approvals in DSO
We confirm the route for your unit.
| Part | Approval route | Guides |
|---|---|---|
| Building NOC Building management or landlord | First. | Building NOC |
| Fit-out permit DSO Authority (DIEZ) | Drawings reviewed. | DIEZ approval |
| Kitchen layout DM Food Safety | Approved again after changes. | Food safety |
| Fire safety and suppression Civil Defence | Kitchen hood system. | Fire suppression |
| Gas Approved LPG provider | Or electric cooking undertaking. | — |
How it works
How we get your DSO approval
1. Review
The unit, the planned works and the drawings you have.
2. Drawings
Existing drawings, or we survey and redraw the unit.
3. Building NOC
From building management or the landlord.
4. DSO Authority
Fit-out or building permit, part of DIEZ.
5. Civil Defence
Fire safety drawings approved.
6. Works
Carried out to the approved drawings.
7. Completion
Inspection and completion before the unit opens.
Who does what
Who approves it in Dubai Silicon Oasis
Building management or landlord
Issues the NOC for the works in your unit. There is no developer NOC in DSO.
Building NOC →DSO Authority (DIEZ)
Issues the fit-out or building permit for works in Dubai Silicon Oasis.
DIEZ approval →Dubai Civil Defence
Approves the fire safety for every commercial fit-out change and inspects before completion.
DSO and DCD →Dubai Municipality Food Safety
Approves the kitchen and food layout of restaurants and cafes.
Food safety layout →Structural Solutions
Prepares the drawings and calculations and handles the submissions as consultant.
Talk to our engineers →What we prepare
Why DSO submissions get returned
- Building management or landlord NOC missing
- Drawings that do not match the unit on site
- Fire safety changes not shown for Civil Defence
- Structural changes without stamped calculations
- Works started before the permit
Questions
Questions tenants and owners ask
Who approves a restaurant fit-out in DSO?
The DSO Authority (DIEZ) after the building NOC, with Civil Defence and DM Food Safety.
Do I need DM Food Safety approval in DSO?
Yes, for the kitchen and food layout, and again after any change.
What about LPG?
The approved LPG provider gives its own approval for the gas system.
What if we cook only with electricity?
An undertaking letter is given instead of the LPG approval.
Is a cafe the same as a restaurant?
Yes, the same route applies.
Related guides
