My Contractor Can’t Get the Completion Certificate (BCC): What to Do
The works are finished, but your contractor says the completion certificate (BCC) cannot be issued. Here is why it happens and how we take over the file, fix what is missing and close the permit.
When a contractor cannot get the completion certificate, the cause is almost always in the file or on site: missing or rejected as-built drawings, works that differ from the approved drawings, an expired permit or contractor licence, a failed inspection, missing test reports or a dispute. The owner can bring in an engineering consultant to audit the file and close it. On Dubai Municipality permits, Resolution 275 of 2024 also lets the owner and consultant apply without the contractor’s consent. The completion certificate is also called the BCC (Building Completion Certificate), and many owners simply call it sign-off.
Diagnose
What the contractor’s answer usually means
Ask the contractor for the exact comment or reason, then match it here.
| What the contractor says | What is usually behind it | Guide |
|---|---|---|
| “The authority rejected the drawings” | As-built drawings missing, wrong or not matching the site | as-built drawings for the completion certificate |
| “The inspector found issues” | Snags or works that differ from the approved drawings | Works don’t match the drawings |
| “The permit expired” | The permit needs renewing before the completion request | Permit expired before completion |
| “My licence is being renewed” | The contractor’s trade licence or registration lapsed | Contractor licence expired |
| “Civil Defence has not approved” | Fire safety completion pending | DCD completion pending |
| “They want test reports” | Concrete or load test reports missing | Structural test reports |
| “The developer will not clear it” | Developer snags or NOC conditions open | Developer clearance |
| No clear answer, or no reply | The file may never have been submitted, or there is a dispute | completion certificate takeover service |
Dubai law
Completion certificate without the contractor on DM permits
Administrative Resolution No. 275 of 2024, Articles 10 to 12, for Dubai Municipality permits.
| Situation | What the resolution says |
|---|---|
| Contractor does not agree | The owner and the consultant can apply without the contractor’s consent, with a technical report from the consultant. |
| Contractor response | Dubai Municipality gives the contractor 7 working days to give reasons. |
| No reply, or a financial or contractual reason | Dubai Municipality proceeds with the completion certificate. |
| Technical or engineering reason | Dubai Municipality checks the issues and decides case by case. |
| Consultant also refuses | The owner can apply; Dubai Municipality may ask for a technical report from an approved engineering consultancy. |
DDA, Trakhees and other areas follow their own rules. We confirm the route for your case.
Options
Your options as the owner
| Option | When it fits |
|---|---|
| Let the contractor finish with our support | The contractor is cooperative but the file needs engineering work |
| Take over the completion file | The contractor is slow, absent or unable; see completion certificate takeover service |
| Change the contractor on the permit | Unfinished works need a new contractor; see contractor change on a DM permit |
| Apply without the contractor’s consent (DM) | Works are finished and the contractor refuses; see contractor refused to sign off |
Official sites: Dubai Municipality | DDA | Trakhees
What you need to know
- Ask for the exact reason: the authority comment tells you what is missing.
- Owner letter: you sign it, not the contractor; see owner letter.
- Dispute is separate: payment issues do not have to block the certificate on DM permits.
- Unfinished works may need a new contractor first.
Documents you will need
- Permit number and approved drawings
- Any rejection or inspection comments
- Photos of the finished works
- Title deed and owner ID
- Contractor contact and contract, if available
How it works
How we close the file when the contractor cannot
1. Get the reason
Comment or rejection.
2. File audit
What is missing.
3. Survey
Works against drawings.
4. Fix
Drawings, site, contractor.
5. Inspections
Developer and authority.
6. BCC
Permit closed.
Already done
Changes made on site without approval?
Built works take an as-built route, not the new works route. A fine may apply, depending on the case. Contact us and we will help you accordingly.
Contact our engineering team on WhatsApp or call us directly on +971 55 339 4451.
Questions
Contractor and completion certificate questions
Why can’t my contractor get the completion certificate?
Usually because something in the file or on site does not match what the authority approved: as-built drawings, changes on site, an expired permit or licence, failed inspections or missing test reports.
My contractor is unable to obtain the BCC. What should I do?
Ask for the exact authority comment, then have a consultant audit the file. We find what is missing and close it with you. See completion certificate takeover service.
Can I get the completion certificate without my contractor?
Yes, in most cases. On DM permits, Resolution 275 of 2024 allows the owner and consultant to apply without the contractor’s consent. See completion certificate without the original contractor.
Does a payment dispute stop the completion certificate?
On DM permits, if the contractor’s reason is financial or contractual, Dubai Municipality proceeds with the certificate. In other areas we confirm the route.
Who signs the completion letter?
The owner signs the owner letter. A contractor completion letter is not what is required.
Do I need a new contractor?
Only if works are unfinished or must be corrected. Then the contractor on the permit is changed first.
Is the completion certificate the same as the BCC?
Yes. The completion certificate is also called the BCC (Building Completion Certificate), and many owners simply call it sign-off.
How much does it cost?
It depends on the drawings and the scope. We review the file and advise.
Who can help?
Structural Solutions takes over stuck completion files. We audit the file, survey the works, prepare the as-built drawings and the owner letter pack, coordinate any contractor change and follow the developer and authority inspections until the completion certificate (BCC) is issued. Contact our engineering team on WhatsApp or call us directly on +971 55 339 4451.