DSO Warehouse Fit-Out Approval: Racking, Mezzanines and Offices

Racking, a mezzanine or an office inside a Dubai Silicon Oasis warehouse needs the landlord NOC, the DSO Authority (DIEZ) permit, Civil Defence and stamped structural calculations.

A warehouse fit-out in Dubai Silicon Oasis starts with the landlord or building management NOC, then the DSO Authority permit, then Civil Defence. High racking and mezzanines add load to the floor and change the fire safety, so they need stamped structural calculations and fire safety drawings. An office or store built inside the warehouse is shown on the same drawings. Fire protection is checked against the storage height and layout.

RackingStamped calculations
MezzanineStructural design
Fire safetyCivil Defence

What you need to know

  • Racking: Height, loads and anchoring checked; fire safety reviewed for the storage.
  • Mezzanine: Steel or concrete design with stamped calculations.
  • Office inside: Partitions, AC and exits shown on the drawings.
  • Floor slab: Checked for racking legs, forklifts and stock.
  • Fire protection: Checked against the storage height and layout.

Documents you will need

  • Lease or title deed, and trade licence for businesses
  • Building management or landlord NOC
  • Existing or as-built drawings of the unit
  • Proposed fit-out drawings, stamped by the consultant
  • Fire safety drawings for Civil Defence
  • Structural calculations where loads or openings change

By type of unit

Warehouse works and what they need

We confirm the route for your unit.

WorkApproval routeGuides
High racking
Calculations and fire safety
DCD reviews the storage.Racking
Mezzanine
Structural design
Stamped calculations.Mezzanines
Office inside the warehouse
Fit-out drawings, DCD
Exits and AC.—
Machinery
Light industrial route
Floor and power.Light industrial

How it works

How we get your DSO approval

1. Review

The unit, the planned works and the drawings you have.

2. Drawings

Existing drawings, or we survey and redraw the unit.

3. Building NOC

From building management or the landlord.

4. DSO Authority

Fit-out or building permit, part of DIEZ.

5. Civil Defence

Fire safety drawings approved.

6. Works

Carried out to the approved drawings.

7. Completion

Inspection and completion before the unit opens.

Who does what

Who approves it in Dubai Silicon Oasis

🏢

Building management or landlord

Issues the NOC for the works in your unit. There is no developer NOC in DSO.

Building NOC →
🏛️

DSO Authority (DIEZ)

Issues the fit-out or building permit for works in Dubai Silicon Oasis.

DIEZ approval →
🚒

Dubai Civil Defence

Approves the fire safety for every commercial fit-out change and inspects before completion.

DSO and DCD →
📐

Structural Solutions

Prepares the drawings and calculations and handles the submissions as consultant.

Talk to our engineers →

Why DSO submissions get returned

  • Building management or landlord NOC missing
  • Drawings that do not match the unit on site
  • Fire safety changes not shown for Civil Defence
  • Structural changes without stamped calculations
  • Works started before the permit

Questions

Questions tenants and owners ask

Who approves a warehouse fit-out in DSO?

The DSO Authority (DIEZ) after the landlord NOC, with Civil Defence.

Does racking need approval in DSO?

Yes, with stamped calculations and fire safety drawings.

Can I add an office inside my warehouse?

Yes, with approval; it is shown on the fit-out drawings.

Can I build a mezzanine?

Often yes, with a structural design and approval.