Jumeirah Golf Estates Villa Mezzanine Approval: JGE NOC and Trakhees
A mezzanine in a Jumeirah Golf Estates villa needs the JGE NOC, then the Trakhees building permit.
In Jumeirah Golf Estates, including Whispering Pines and the other clusters, a villa mezzanine needs the JGE NOC from the JGE NOC team on behalf of wasl, through the JGE Portal or the Wasl App, then the Trakhees building permit with the same stamped drawings and calculations. It counts as added GFA, and Civil Defence approval is needed.
What you need to know
- All JGE clusters: Whispering Pines, Redwood Avenue, Sienna Lakes and the others.
- JGE NOC first: Then Trakhees.
- Structure: Slab and walls checked.
Documents you will need
- Title deed and Emirates ID of the owner
- Approved or as-built drawings of the villa
- Mezzanine drawings with stamped structural calculations
- Developer or master community NOC
- Fire safety drawings for Civil Defence
By situation
Villa mezzanine route by community
We confirm the route for your building and area.
| Community | Approval route | Guides |
|---|---|---|
| Nakheel communities (Palm, Jumeirah Park, Jumeirah Islands, Al Furjan) Nakheel NOC, then Trakhees | Counts as GFA. | Trakhees villas |
| Jumeirah Golf Estates JGE NOC, then Trakhees | Counts as GFA. | JGE |
| Jebel Ali Village Nakheel NOC, then Trakhees | Counts as GFA. | Jebel Ali Village |
| Emaar communities such as Arabian Ranches and Dubai Hills Emaar NOC, then DDA | Counts as GFA. | — |
| Dubai Municipality areas Approved consultant submits to DM | Counts as GFA. | — |
How it works
How we get your mezzanine approved
1. Site and slab review
The unit, the existing slab and columns, and what the mezzanine is for.
2. Existing drawings
From the landlord, developer or authority; if missing or out of date, we survey and draw as built.
3. Design and calculations
Mezzanine drawings, steel design and stamped structural calculations, with the added floor area shown.
4. NOC
Landlord, building management or master developer NOC.
5. Permit and Civil Defence
The authority for the area approves the structure; the approved steel contractor stamps the steel; DCD approves fire safety.
6. Build, inspect, complete
The mezzanine is built as approved, inspected, and the completion certificate is issued.
Who does what
Who approves a villa mezzanine
Master developer
Gives the NOC for the villa, through its portal or community team.
Authority for the community
Dubai Municipality, DDA or Trakhees issues the building permit.
Villa route →What we prepare
- Design and stamped calculations
- JGE NOC and Trakhees permit
Why mezzanine submissions get returned
- Mezzanine built before approval
- No landlord or developer NOC
- Drawings that do not match the unit as built
- Slab and columns not checked for the new loads
- Steel without the approved steel contractor stamp
- Added floor area not shown
- No Civil Defence fire safety drawings
Questions
Questions villa owners ask
Who approves a mezzanine in Jumeirah Golf Estates?
JGE gives the NOC, Trakhees issues the permit.
Is Whispering Pines the same?
Yes, the same route.
Does it count as GFA?
Yes.
Related guides
