Expo City · Question

Do I Need DCAA Approval in Expo City?

No. Works in Expo City are approved by Expo City Dubai Authority (ECDA), with Civil Defence for commercial units. DCAA is not part of the route.

No. DCAA (Dubai Civil Aviation Authority) approval is not needed for works in Expo City. The NOC and approval come from Expo City Dubai Authority (ECDA). Restaurants, shops and offices also need Dubai Civil Defence approval, and restaurants need the kitchen layout approved by Dubai Municipality (DM) Food Safety. DCAA approval applies to projects in Dubai South, including Emaar South, which is a different area with its own authority.

DCAANot needed in Expo City
AuthorityECDA
Dubai SouthDCAA needed

What you need to know

  • Expo City: ECDA, plus Civil Defence for commercial units.
  • Restaurants: Plus DM Food Safety.
  • Dubai South: Dubai South Authority, then DCAA.

Documents you will need

  • Trade licence and lease, or title deed for owners
  • Landlord or community NOC where applicable
  • Existing or as-built drawings of the unit
  • Fit-out or modification drawings, stamped by the consultant
  • Fire safety drawings for Civil Defence

By property

Expo City or Dubai South?

We confirm the requirements for your unit.

AreaApproval routeGuides
Expo City Dubai
ECDA, DCD
No DCAA.Expo City
Dubai South
Dubai South Authority, DCAA, DCD
DCAA needed.Dubai South DCAA
Emaar South
Emaar NOC, Dubai South Authority, DCAA
DCAA needed.Emaar South

How it works

How we get your Expo City approval

1. Review

The unit, what you want to change and the drawings you have.

2. Drawings

Existing drawings, or a survey; then the fit-out or modification drawings.

3. ECDA

NOC and approval from Expo City Dubai Authority.

4. Civil Defence

Fire safety drawings approved by DCD.

5. Works

The works follow the approved drawings.

6. Inspection

DCD final inspection and completion before opening.

Who does what

Who approves works in Expo City

🏛️

Expo City Dubai Authority (ECDA)

Issues the NOCs and approvals for works in Expo City, as its free zone and community authority.

Who approves? →
🚒

Dubai Civil Defence

Approves fire safety for restaurants, shops and offices, and inspects before opening.

Civil Defence in Expo City →
🍽️

Dubai Municipality Food Safety

Restaurants and cafés also need the kitchen layout approved by Dubai Municipality (DM) Food Safety.

DM food safety →

Why Expo City submissions get returned

  • Drawings that do not match the unit
  • Fire safety changes without DCD approval
  • Kitchen layout not approved by DM Food Safety
  • Gas works without DCD approval
  • Works started before approval

Questions

Questions tenants and owners ask

Is DCAA approval needed in Expo City?

No.

Who approves works in Expo City?

Expo City Dubai Authority (ECDA).

Where is DCAA approval needed?

For projects in Dubai South, including Emaar South.