What NOCs Are Needed for a New Villa on a Meraas Plot?

Owners ask for "the NOC" for their plot. A new villa on a Meraas plot needs several, issued at different stages by DCM, Civil Defence and DDA.

A new villa on a Meraas plot needs these approvals, in order: the affection plan and plot rules from DCM, the DCM community NOC on the design, Civil Defence approval and the DDA building permit. Before and during construction, DCM issues the site NOCs (hoarding, site access, mobilization), the sewerage connection NOC, the vehicle access and gate level NOC, and a right of way NOC for any road works, with RTA after it. The utility connections follow the DCM NOCs. At the end, the DCM and Civil Defence completions come before the DDA completion certificate. We obtain all of them.

FirstDCM design NOC
PermitDDA
Site NOCsWe obtain them

The list

Every NOC and approval, in order

#NOC or approvalIssued byWhen
1Affection plan and plot rulesDCMBefore design
2Community NOC on the designDCMDesign stage
3Fire safety approvalCivil DefenceBefore the permit
4Building permitDDABefore works
5Hoarding, site access, mobilizationDCMBefore works
6Night works (if needed)DCMConstruction
7Sewerage connectionDCMDesign, then completion
8Vehicle access and gate levelDCMDesign, then completion
9Right of way (road works)DCM, then RTABefore road works
10Utility connectionsService providersAfter DCM NOCs
11Completions and BCCDCD, DCM, DDAEnd of works

Communities

Meraas plot communities under DCM

Official sites: DDA | Dubai Civil Defence | RTA | DEWA

What you need to know

  • Several NOCs, not one.
  • DCM first.
  • DDA permit before works.
  • We obtain them all.

Documents you will need

  • Affection plan and plot rules
  • Title deed
  • Approved design drawings
  • Contractor details for site NOCs

How it works

NOCs in order

1. Design NOC

DCM.

2. Fire

DCD.

3. Permit

DDA.

4. Site

DCM NOCs.

5. Services

Sewer, access.

6. Close

Completions.

Questions

NOCs: questions

Which NOC comes first on a Meraas plot?

The DCM community NOC on the design, after the plot rules.

Do I need a separate road NOC?

Only if works reach the road or verge: DCM right of way NOC, then RTA.

Is there a night works NOC?

Yes, from DCM, if works must run at night.

Who applies for the site NOCs?

We obtain them with your contractor.

Who approves overall?

See who approves villa construction on Meraas plots.

How much do the approvals cost?

Our fee depends on the drawings and the scope; we review your plot and advise. The DCM, DDA, Civil Defence and service provider fees are separate, and we list them for your villa before you commit.

Who can help?

Structural Solutions obtains every NOC for new villas on Meraas plots. Contact our engineering team on WhatsApp or call us directly on +971 55 339 4451.