Meraas Plots: New Villa Completion Certificate (BCC)
The building completion certificate (BCC) closes a new villa project on a Meraas plot. Owners also call it the completion certificate or sign-off.
To get the building completion certificate for a new villa on a Meraas plot, the villa must be built as approved and pass the DDA inspections. Civil Defence carries out its final inspection, and DCM completes the sewerage connection, the vehicle access and any right of way works. With those in place and the as-built drawings submitted, DDA issues the BCC. The DEWA connection and moving in follow it. We prepare the completion file and follow each step.
Completion file
What the BCC needs
| Item | From |
|---|---|
| Works built as approved | Contractor, checked by us |
| DDA inspections passed | DDA |
| Civil Defence final inspection | DCD |
| Sewerage connection completion | DCM |
| Vehicle access completion | DCM |
| Right of way completion (if any) | DCM |
| As-built drawings and test reports | Structural Solutions and the contractor |
Communities
Meraas plot communities under DCM
| Community | Guide |
|---|---|
| Pearl Jumeirah | Pearl Jumeirah villa approvals |
| Naia Island | Naia Island villa approvals |
| Jumeirah Bay | Jumeirah Bay villa approvals |
| La Mer | La Mer villa approvals |
| Al Wasl Meraas Plots (Le Hemaira) | Al Wasl Meraas Plots (Le Hemaira) villa approvals |
| Umm Al Sheif Meraas Plots | Umm Al Sheif Meraas Plots villa approvals |
Official sites: DDA | Dubai Civil Defence
What you need to know
- DDA issues the BCC.
- DCD final inspection.
- DCM completions first.
- As-builts needed.
Documents you will need
- DDA permit and approved drawings
- Inspection records
- As-built drawings
- Test reports
How it works
Getting the BCC
1. Finish
As approved.
2. DDA
Inspections.
3. DCD
Final inspection.
4. DCM
Completions.
5. File
As-builts.
6. DDA
BCC.
Questions
Completion certificate: questions
Who issues the completion certificate on a Meraas plot?
DDA, after the Civil Defence and DCM completions.
Does DCM issue a completion?
DCM completes the sewerage, vehicle access and right of way items, which DDA needs before the BCC.
Is a Civil Defence inspection needed?
Yes, a final inspection for every new villa.
When can DEWA connect the villa?
After the completion steps; we coordinate it.
Where does the process start?
How much do the approvals cost?
Our fee depends on the drawings and the scope; we review your plot and advise. The DCM, DDA, Civil Defence and service provider fees are separate, and we list them for your villa before you commit.
Who can help?
Structural Solutions prepares the completion file for new villas on Meraas plots. Contact our engineering team on WhatsApp or call us directly on +971 55 339 4451.