Sobha Hartland · Utilities · Updated November 2026

Sobha Hartland Plot Utilities: Power, Water, Sewer and Gas Rules

Each plot gets fixed utility allocations. Designing within them from day one avoids a redesign later.

Every Sobha Hartland plot has an allocated total connected load from DEWA, and no extra load is given, so the villa must be designed within it. The owner applies to DEWA for electricity and water. LPG cylinders are not allowed. Foul water drains by gravity to the community sewer at the manhole shown in the infrastructure layout. Stormwater discharges onto the road, never into the parks. Refuse is stored inside the plot to Dubai Municipality rules. Telecom comes through Etisalat or du.

PowerAllocated load only
GasNo LPG
StormwaterTo the road

Services

Each service and its rule

ServiceRule
ElectricityWithin the allocated total connected load; owner applies to DEWA
Potable waterOwner applies to DEWA for the connection
GasLPG cylinders not allowed; electric kitchen
SewerageGravity drainage to the community sewer at the allocated manhole
StormwaterFree discharge onto the road; not into parks
IrrigationTSE only for public areas; no plot connection
RefuseStored inside the plot to DM rules
TelecomEtisalat or du
Fire fightingAny plot network independent of the community network

Official sites: Dubai Municipality | DEWA

What you need to know

  • No extra electrical load.
  • No LPG.
  • Sewer by gravity.
  • Undertaking on loads.

Documents you will need

  • Infrastructure layout for the plot
  • Allocated loads on the plot sheet
  • MEP design
  • DEWA application details

How it works

Getting services right

1. Loads

Check allocation.

2. Design

MEP within it.

3. Undertake

To Sobha.

4. Connect

DEWA.

Questions

Utilities: questions

Can I ask for more power later?

No additional connected load is provided, so design within the allocation.

Can I use a gas cylinder?

No. LPG cylinders are not allowed.

Where does my sewer connect?

At the manhole shown in the infrastructure layout for your plot.

Can I irrigate with TSE?

No. TSE serves public areas only.

How much does it cost?

Our fee depends on the drawings and the scope; we review and advise. Sobha, Dubai Municipality and service provider fees are separate.

Who can help?

Structural Solutions designs the villa services within the Sobha allocations. Contact our engineering team on WhatsApp or call us directly on +971 55 339 4451.