RTA Trial Trenches NOC: Digging to Locate Utilities in the Road Reserve
Trial trenches dug inside the road reserve to find existing utilities need an RTA right-of-way NOC before any digging starts.
The short answer
Trial trenches are small excavations that confirm where existing pipes and cables really are before a utility crossing, an access or other works. When they are dug inside the public road reserve, they need an RTA right-of-way (ROW) NOC before digging. The application shows the position and size of each trench and, if a lane or footpath is affected, the traffic or pedestrian layout. The trenches are backfilled and the surface reinstated as approved.
What you need to know
- Why dig: Drawings of existing services are not always accurate.
- Position: Each trench shown on the layout.
- Traffic: A closure layout if a lane or footpath is affected.
- Afterwards: Results feed the crossing or access design.
Documents you will need
- Affection plan showing the plot and the road reserve
- Site layout showing where the works enter the road reserve
- Drawings of the works: plans, sections and details
- Traffic management or diversion layout where the road or footpath is affected
- Stamped structural calculations where something is built or lifted
- Contractor details
By type of work
Which RTA approval for which work
We confirm which RTA approval your works need.
| Work | Approval route | Guides |
|---|---|---|
| Excavation or utility crossing RTA ROW NOC | Before digging in the road reserve. | Utility crossings |
| Trial trenches RTA ROW NOC | To locate existing services. | Trial trenches |
| Hoarding in the road reserve RTA ROW NOC | Not needed if fully inside the plot. | Hoarding |
| Crane or truck on the road RTA permit | Plus road or lane closure. | Crane permit |
| Closing a footpath or lane RTA closure permit | With a traffic layout. | Footpath closure |
| Driveway or kerb cut RTA access permit | For the plot access. | Driveway NOC |
How it works
How the RTA NOC works
1. Site check
Are the works inside the road reserve? Checked against the affection plan.
2. Drawings
Layout, sections and details of the works in the road reserve.
3. Calculations
Stamped structural calculations where needed.
4. Traffic layout
Diversion, lane or footpath closure layout if the road is affected.
5. RTA NOC
Application to RTA; comments answered.
6. Works
Only inside the approved area, after the NOC.
7. Reinstatement
The road, kerb or footpath is reinstated as approved.
Who does what
Who is involved
RTA (Roads and Transport Authority)
Issues the right-of-way (ROW) NOC for works inside the public road reserve.
What is a ROW NOC? →Traffic management
Where a lane, road or footpath is affected, the diversion or closure layout is approved too.
Lane closures →Structural Solutions
Prepares the drawings, layouts and stamped calculations for the RTA application.
Talk to our engineers →What we prepare
- Trial trench layout
- Utility crossing design
Why RTA applications get returned
- Works shown outside the approved area
- No traffic management layout where lanes or footpaths are affected
- Drawings that do not match the site
- Missing structural calculations
- Works started before the NOC
Questions
Questions owners and contractors ask
Do trial trenches need an RTA NOC?
Yes, when they are inside the road reserve.
Do trenches inside my plot need it?
No ROW NOC is needed for digging fully inside the plot.
What do the drawings show?
The position and size of each trench, and any traffic layout.