RTA · Trial trenches

RTA Trial Trenches NOC: Digging to Locate Utilities in the Road Reserve

Trial trenches dug inside the road reserve to find existing utilities need an RTA right-of-way NOC before any digging starts.

The short answer

Trial trenches are small excavations that confirm where existing pipes and cables really are before a utility crossing, an access or other works. When they are dug inside the public road reserve, they need an RTA right-of-way (ROW) NOC before digging. The application shows the position and size of each trench and, if a lane or footpath is affected, the traffic or pedestrian layout. The trenches are backfilled and the surface reinstated as approved.

ApprovalRTA ROW NOC
BeforeAny digging
ThenBackfill and reinstate

What you need to know

  • Why dig: Drawings of existing services are not always accurate.
  • Position: Each trench shown on the layout.
  • Traffic: A closure layout if a lane or footpath is affected.
  • Afterwards: Results feed the crossing or access design.

Documents you will need

  • Affection plan showing the plot and the road reserve
  • Site layout showing where the works enter the road reserve
  • Drawings of the works: plans, sections and details
  • Traffic management or diversion layout where the road or footpath is affected
  • Stamped structural calculations where something is built or lifted
  • Contractor details

By type of work

Which RTA approval for which work

We confirm which RTA approval your works need.

WorkApproval routeGuides
Excavation or utility crossing
RTA ROW NOC
Before digging in the road reserve.Utility crossings
Trial trenches
RTA ROW NOC
To locate existing services.Trial trenches
Hoarding in the road reserve
RTA ROW NOC
Not needed if fully inside the plot.Hoarding
Crane or truck on the road
RTA permit
Plus road or lane closure.Crane permit
Closing a footpath or lane
RTA closure permit
With a traffic layout.Footpath closure
Driveway or kerb cut
RTA access permit
For the plot access.Driveway NOC

How it works

How the RTA NOC works

1. Site check

Are the works inside the road reserve? Checked against the affection plan.

2. Drawings

Layout, sections and details of the works in the road reserve.

3. Calculations

Stamped structural calculations where needed.

4. Traffic layout

Diversion, lane or footpath closure layout if the road is affected.

5. RTA NOC

Application to RTA; comments answered.

6. Works

Only inside the approved area, after the NOC.

7. Reinstatement

The road, kerb or footpath is reinstated as approved.

Who does what

Who is involved

🛣️

RTA (Roads and Transport Authority)

Issues the right-of-way (ROW) NOC for works inside the public road reserve.

What is a ROW NOC? →
🚧

Traffic management

Where a lane, road or footpath is affected, the diversion or closure layout is approved too.

Lane closures →
📐

Structural Solutions

Prepares the drawings, layouts and stamped calculations for the RTA application.

Talk to our engineers →

What we prepare

Why RTA applications get returned

  • Works shown outside the approved area
  • No traffic management layout where lanes or footpaths are affected
  • Drawings that do not match the site
  • Missing structural calculations
  • Works started before the NOC

Questions

Questions owners and contractors ask

Do trial trenches need an RTA NOC?

Yes, when they are inside the road reserve.

Do trenches inside my plot need it?

No ROW NOC is needed for digging fully inside the plot.

What do the drawings show?

The position and size of each trench, and any traffic layout.

Related guides

Keep reading