RTA Parking Reservation for Construction Works in Dubai
When a crane, concrete pump or delivery trucks need to stand on public parking bays, or the bays are needed for a temporary site access, they must be reserved first: RTA approves, then Parkin reserves the bays.
Public parking bays next to a construction site can only be used for the works with approval. The RTA approves the use of the bays for the construction activity, and Parkin then reserves and blocks the bays for the works. It is needed when a crane, concrete pump or delivery trucks stand on the parking bays, or when bays are blocked to create a temporary site access. We prepare the layout drawing showing the bays, the crane or truck position and the access, and handle the applications for the contractor or owner.
What you need to know
- RTA first: The use of the bays for the works is approved by RTA.
- Then Parkin: Parkin reserves and blocks the approved bays.
- Cranes and pumps: The crane or pump position and outriggers are shown on the layout.
- Trucks: Delivery trucks standing on the bays need the bays reserved.
- Site access: Bays blocked for a temporary site entrance are shown on the drawing.
- Not without approval: Using the bays without approval can lead to violations.
Documents you will need
- Trade licence of the contractor
- Building permit or project details
- Site plan showing the parking bays to be used
- Crane, pump or truck position, where relevant
- Temporary site access layout, where relevant
By situation
When you need a parking reservation
We confirm the requirements for your project.
| Activity | Approval route | Guides |
|---|---|---|
| Crane or concrete pump on the bays RTA approval, then Parkin | Position and outriggers shown. | RTA crane permit |
| Delivery trucks on the bays RTA approval, then Parkin | Trucks standing while unloading. | Truck permit |
| Temporary site access over the bays RTA approval, then Parkin | Access shown on the layout. | Vehicle access |
| Works also closing a lane Plus a road closure permit | Diversion layout needed. | Road closure permit |
How it works
How we get the bays reserved
1. Site check
Which bays are needed and for what.
2. Layout drawing
Bays, crane or truck position and access.
3. RTA application
Approval of the use of the bays.
4. Parkin
Bays reserved and blocked after the RTA approval.
5. Works
Carried out on the reserved bays only.
Who does what
Who approves it
Parkin
After the RTA approval, Parkin reserves and blocks the parking bays for the works.
Parking reservation →Structural Solutions
Prepares the layout drawing of the bays, the crane or truck position and the site access, and handles the applications.
Talk to our engineers →Related RTA permits
Why applications come back
- Bays not shown clearly on the layout
- Crane or truck position missing
- Access across the footpath not shown
- Lane closure needed but not applied for
Questions
Questions contractors ask
Who reserves public parking bays for construction in Dubai?
RTA approves the use of the bays, then Parkin reserves and blocks them.
When do I need to reserve parking bays?
When a crane, concrete pump or trucks stand on the bays, or the bays are used for a temporary site access.
Can I just put cones on the bays?
No, the bays must be approved and reserved first.
Who applies?
We prepare the layout and handle the applications for the contractor or owner.
What if the works also close a lane?
A road closure permit with a diversion layout is needed as well.