Right of Way (ROW) NOC for Villa Works on a Meraas Plot
Anything your contractor does outside the plot limit, in the road or the verge, is a right of way work. On the Meraas plots, DCM approves it first.
Works outside the plot limit on a Meraas plot need a DCM right of way (ROW) NOC: laying cables or pipes to the villa, crossing the road, moving a light pole or a cabinet, trial pits, verge landscaping, and road closures or diversions for cranes and deliveries. Where the works reach a public road, RTA approval follows the DCM NOC. When the works are finished, DCM completes the right of way works, which is needed before the completion certificate. We prepare the drawings and the traffic plan where needed.
ROW works
Works that need the NOC
| Work | Example |
|---|---|
| Cable and pipe laying | Power, water or telecom to the villa |
| Road crossing | Service line under the road |
| Service relocation | Moving a light pole or a cabinet |
| Trial pit | Locating existing services |
| Landscaping | Verge planting by the plot |
| Road closure or diversion | Crane, deliveries, road crossing |
Order
Who approves, in order
| Step | Who |
|---|---|
| Right of way NOC | DCM |
| Public road works | RTA; see RTA road works |
| Works | Contractor |
| Completion | DCM |
Communities
Where this applies
The same step applies on the Meraas plots in Pearl Jumeirah, Naia Island, Jumeirah Bay, La Mer, Al Wasl (Le Hemaira) and Umm Al Sheif.
| Community | Guide |
|---|---|
| Pearl Jumeirah | Pearl Jumeirah villa approvals |
| Naia Island | Naia Island villa approvals |
| Jumeirah Bay | Jumeirah Bay villa approvals |
| La Mer | La Mer villa approvals |
| Al Wasl (Le Hemaira) | Al Wasl (Le Hemaira) villa approvals |
| Umm Al Sheif | Umm Al Sheif villa approvals |
Official sites: RTA
What you need to know
- Outside the plot = ROW.
- DCM first.
- RTA for public roads.
- Completion before BCC.
Documents you will need
- Site plan with plot limit
- Drawings of the works
- Traffic plan, if a closure
- Contractor details
How it works
ROW steps
1. Scope
Works outside plot.
2. Drawings
And traffic plan.
3. DCM
ROW NOC.
4. RTA
If public road.
5. Works
Contractor.
6. Complete
DCM.
Questions
Right of way: questions
What is a right of way work?
Any work outside the plot limit, in the road or the verge.
Who approves it on a Meraas plot?
DCM first, then RTA where it is a public road.
Do I need it for a crane on the road?
Yes, for a road closure or diversion.
Is the ROW completion needed for the BCC?
Yes. See the completion certificate.
How much does it cost?
Our fee depends on the drawings and the scope; we review your plot and advise. DCM, DDA, Civil Defence and service provider fees are separate, and we list them before you commit.