Right of Way (ROW) NOC for Villa Works on a Meraas Plot

Anything your contractor does outside the plot limit, in the road or the verge, is a right of way work. On the Meraas plots, DCM approves it first.

Works outside the plot limit on a Meraas plot need a DCM right of way (ROW) NOC: laying cables or pipes to the villa, crossing the road, moving a light pole or a cabinet, trial pits, verge landscaping, and road closures or diversions for cranes and deliveries. Where the works reach a public road, RTA approval follows the DCM NOC. When the works are finished, DCM completes the right of way works, which is needed before the completion certificate. We prepare the drawings and the traffic plan where needed.

FirstDCM ROW NOC
Public roadRTA after DCM
EndROW completion

ROW works

Works that need the NOC

WorkExample
Cable and pipe layingPower, water or telecom to the villa
Road crossingService line under the road
Service relocationMoving a light pole or a cabinet
Trial pitLocating existing services
LandscapingVerge planting by the plot
Road closure or diversionCrane, deliveries, road crossing

Order

Who approves, in order

StepWho
Right of way NOCDCM
Public road worksRTA; see RTA road works
WorksContractor
CompletionDCM

Communities

Where this applies

The same step applies on the Meraas plots in Pearl Jumeirah, Naia Island, Jumeirah Bay, La Mer, Al Wasl (Le Hemaira) and Umm Al Sheif.

Official sites: RTA

What you need to know

  • Outside the plot = ROW.
  • DCM first.
  • RTA for public roads.
  • Completion before BCC.

Documents you will need

  • Site plan with plot limit
  • Drawings of the works
  • Traffic plan, if a closure
  • Contractor details

How it works

ROW steps

1. Scope

Works outside plot.

2. Drawings

And traffic plan.

3. DCM

ROW NOC.

4. RTA

If public road.

5. Works

Contractor.

6. Complete

DCM.

Questions

Right of way: questions

What is a right of way work?

Any work outside the plot limit, in the road or the verge.

Who approves it on a Meraas plot?

DCM first, then RTA where it is a public road.

Do I need it for a crane on the road?

Yes, for a road closure or diversion.

Is the ROW completion needed for the BCC?

Yes. See the completion certificate.

How much does it cost?

Our fee depends on the drawings and the scope; we review your plot and advise. DCM, DDA, Civil Defence and service provider fees are separate, and we list them before you commit.