Quick answer

Every Emaar villa needs an Emaar NOC first, but the building permit depends on the community. Emaar DM or DDA comes down to this: Emirates Living (The Springs, Meadows, Lakes, Emirates Hills, The Greens and The Views) goes to Dubai Municipality. Arabian Ranches, Dubai Hills Estate and The Valley go to DDA.

Last checked: November 2026. Official sources: Emaar · Dubai Municipality · DDA

Many owners and contractors assume that one developer means one authority. With Emaar that is not the case. Two villas built by the same developer can go to different authorities, and a submission to the wrong one wastes time.

Which authority applies to your community

CommunityDeveloper stepBuilding permit
The SpringsEmaar NOCDubai Municipality
The MeadowsEmaar NOCDubai Municipality
The LakesEmaar NOCDubai Municipality
Emirates HillsEmaar NOCDubai Municipality
Arabian Ranches 1, 2 and 3Emaar NOCDDA
Dubai Hills EstateEmaar NOCDDA
The ValleyEmaar NOCDDA
Emaar SouthEmaar NOCDubai South Authority, plus DCAA

Emaar South is the exception many people miss: it is neither DM nor DDA. The full list of areas is in our community authority directory.

Dubai Hills sub-communities

Fairways, Hills Views and Majestic Villas are part of Dubai Hills Estate, so they follow Emaar and then DDA. See is Dubai Hills under DM, DDA or Trakhees.

What stays the same

  • The NOC is applied for.
  • Emaar provides villa plans to owners.
  • Works start only after the building permit is issued.
  • Structural works need stamped structural calculations.
  • At the end, Emaar inspects, issues its clearance and releases the security deposit.

What changes

Apartments in Emaar buildings

Apartments follow a different route, starting with the building management NOC. For example, see merging apartments in Dubai.

Questions owners ask

Is The Springs under DM or DDA?

Dubai Municipality. All of Emirates Living goes through Emaar and then Dubai Municipality.

Is Emirates Hills under DDA?

No. Emirates Hills goes through Emaar and then Dubai Municipality.

Is Arabian Ranches under DM or DDA?

DDA. Arabian Ranches 1, 2 and 3 go through Emaar and then DDA.

Is Dubai Hills Estate under DM or DDA?

DDA, including Fairways, Hills Views and Majestic Villas.

Is Emaar South under DDA?

No. Emaar South goes through Emaar and then Dubai South Authority, plus DCAA.

Does the Emaar NOC replace the building permit?

No. The NOC is the developer step. The building permit comes from the authority, and works start only after it is issued.

Related service

Emaar approvals

We confirm the authority for your villa, prepare the drawings and calculations, and handle the Emaar NOC and the building permit.

Emaar approvals →Find my authority →

Ask which authority applies

Need this approved?

Send us photos and the location. We will tell you which approvals apply and handle them for you.