Dubai Holding · Site access

Dubai Holding construction site access NOC: hoarding, mobilization and laydown

Before a contractor starts on a plot in a Dubai Holding community, the site needs access NOCs: hoarding on the plot boundary, construction site access, mobilization, and access for soil investigation, surveys and piling. Using land next to the plot needs a laydown NOC. We submit them for you.

The short answer

The portal groups these under temporary construction access, fence on plot limits, and mobilization and lay down. There is a NOC for the hoarding at the plot boundary, for construction site access, for mobilization, and for access to carry out soil investigation, shoring and piling, and topographic, traffic impact or environmental studies. Using land outside the plot for storage needs the temporary site utilisation / fence laydown NOC.

Before studiesSurvey and soil investigation access
Before worksHoarding and construction site access
LaydownTemporary site utilisation NOC
ApplicationsNew or renewal

Site access NOCs

  • Hoarding: Temporary site fence at the plot boundary
  • Site access: Construction site access
  • Mobilization: Setting up the site
  • Soil investigation: Access for soil tests
  • Shoring and piling: Access inside the plot limits
  • Studies: Topographic survey, traffic impact, environmental

Documents you will need

  • Site layout with hoarding and access (we prepare this)
  • Title deed and affection plan
  • Owner letter
  • Contractor or survey company trade licence
  • Planned start date and duration

NOC types

Site access NOC types

Pick the one for your stage of works.

NOCApproval routeGuides
Temporary site fence (hoarding) at plot boundary
Dubai Holding
Hoarding installed on the plot limits. New or renewal.RTA hoarding NOC
Temporary construction site access
Dubai Holding
Construction access to the plot. New or renewal.—
Mobilization
Dubai Holding
Setting up the site for works. New or renewal.—
Plot soil investigation site access
Dubai Holding
Access for soil tests. New or renewal.Soil test
Shoring and piling works site access (inside plot limits)
Dubai Holding
Access for shoring and piling rigs. New or renewal.Shoring permit
Topographic survey, traffic impact, environmental studies site access
Dubai Holding
Access for surveys and studies. New or renewal.Traffic Impact Study
Temporary site utilisation / fence laydown
Dubai Holding
Using land outside the plot for storage or laydown.—

How it works

How we get it done

1. Studies access

Soil investigation and surveys.

2. Design and permits

Drawings and approvals for the works.

3. Hoarding

Hoarding NOC at the plot boundary.

4. Site access

Construction site access and mobilization.

5. Piling

Shoring and piling access.

6. Laydown

If land outside the plot is needed.

What owners ask us about

Common reasons for comments

  • Hoarding outside the plot limits
  • Site works started before the access NOC
  • Laydown outside the plot without a NOC
  • NOC expired during the works

Starting work on site?

Get your site access NOCs

Send us three things on WhatsApp:

  1. Your community and plot number
  2. What stage the project is at
  3. Your contractor or survey company

We prepare the layouts and submit the Dubai Holding site access NOCs.

Questions

Questions

Do I need a NOC before my contractor starts in a Dubai Holding community?

Yes. The contractor needs the hoarding and construction site access NOCs, and the mobilization NOC to set up the site.

Do I need a NOC for a soil investigation?

Yes, the plot soil investigation site access NOC.

Do I need a NOC for a topographic survey?

Yes. Topographic surveys, traffic impact studies and environmental studies have a site access NOC.

What are the hoarding rules on the plot boundary?

The hoarding NOC covers a temporary site fence installed on the plot limits. We prepare the layout.

Do I need site access for shoring and piling?

Yes, the shoring and piling works site access NOC, for work inside the plot limits.

Can I store materials on the land next to my plot?

Only with the temporary site utilisation / fence laydown NOC.

Can site access NOCs be renewed?

Yes, if the works run longer.

Do I still need the building permit?

Yes. Site access NOCs do not replace the building permit from the authority for your area.

Who can apply for a Dubai Holding NOC?

Only registered consultants and contractors can apply on the Dubai Holding Community Management NOC portal. Owners cannot apply themselves. We are registered and submit for our clients.