DDA approval process: developer NOC, DCM and the DDA permit

The DDA approval process starts with the developer NOC, then an approved consultant submits the drawings and stamped calculations to the Dubai Development Authority for the building permit. Infrastructure NOCs in DCM communities also go through the DDA portal.

The short answer

In Dubai Development Authority (DDA) communities, the master developer's NOC comes first, then an approved consultant submits to DDA for the building permit. Infrastructure requests in Dubai Community Management (DCM) master communities have been submitted through the DDA portal since 25 March 2024. Planning changes such as additional GFA or height stay with the master developer's planning team. After the works, DDA inspects and issues the completion certificate.

FirstDeveloper NOC
Submitted byApproved consultant
DCMInfrastructure NOCs via the DDA portal
CompletionNo extra floor area at completion

DDA approval process: what you need to know

  • Developer NOC: Emaar, DAMAC, MAF, Al Aryam, Dubai Holding or building management
  • DDA permit: Submitted by an approved consultant
  • DCM: Infrastructure NOCs through the DDA portal since 25 March 2024
  • Planning changes: GFA, height, land use and plot merging stay with the developer's planning team
  • Shoring: Required where applicable
  • Pools: Plus the DM Environment Department NOC

Documents you will need

  • Title deed and owner ID
  • Affection plan
  • Developer NOC (we apply for it)
  • Existing drawings (we obtain them or survey)
  • Proposed drawings and stamped calculations (we prepare these)

By community

Who issues the NOC before DDA

We confirm the route for your plot.

CommunityApproval routeGuides
Arabian Ranches, Dubai Hills, The Valley, Emaar South
Emaar → DDA
Emaar NOC through the Emaar Community Portal, then DDA.Emaar
DAMAC Hills and DAMAC Hills 2
DAMAC → DDA
DAMAC NOC by email, then DDA.DAMAC
Tilal Al Ghaf
Majid Al Futtaim → DDA
MAF NOC through the MAF app, then DDA.Tilal Al Ghaf
Mira and Mira Oasis
Al Aryam → DDA
Al Aryam NOC, then DDA.Mira
Mudon, Villanova, Serena
Dubai Holding → DDA
Dubai Holding Portal, then DDA.Mudon
Town Square
Developer → DDA
Developer NOC by app or email, then DDA.Town Square
Business Bay
Building management → DDA
Building management NOC, then DDA.—
TECOM zones
DDA
Fit-outs through the DDA portal; restaurants also need DM Food Safety.TECOM

How it works

From idea to DDA permit

1. Your idea

Community and scope.

2. Developer NOC

We apply to the master developer.

3. Drawings

Drawings, stamped calculations and shoring where needed.

4. DDA submission

By an approved consultant.

5. Comments

We answer and resubmit.

6. Completion

Inspection and completion certificate.

Common reasons DDA delays

  • Missing developer NOC
  • Drawings not matching the villa as built
  • Extra floor area added at completion
  • Missing stamped calculations or shoring design

Need DDA approval?

Get your DDA route today

Send us three things on WhatsApp:

  1. Your community and plot or unit number
  2. Photos of the area
  3. What you want to build or change

We get the developer NOC, prepare the drawings and submit to DDA as your consultant.

Questions

DDA approval process: questions

How does the DDA approval process work?

The developer NOC comes first, then an approved consultant submits the drawings and stamped calculations to the Dubai Development Authority (DDA) for the building permit, followed by inspection and completion.

Can I apply to DDA myself?

No. DDA submissions are made by an approved consultant. We submit for you.

Which communities are under DDA?

Including Arabian Ranches, Dubai Hills, The Valley, Emaar South, DAMAC Hills, Tilal Al Ghaf, Mira, Town Square, Mudon, Villanova, Business Bay and the TECOM zones.

Do I need a developer NOC before DDA?

Yes in master communities: Emaar, DAMAC, Majid Al Futtaim, Al Aryam, Dubai Holding or the building management, depending on the community.

What is DCM and what does it approve?

Dubai Community Management handles infrastructure NOCs in its master communities, submitted through the DDA portal since 25 March 2024.

Who approves extra floor area or height changes?

Planning changes such as additional GFA, height, land use or plot merging go to the master developer's planning team, not only DDA.

Can I add floor area at completion in DDA areas?

No. DDA does not allow extra floor area at completion; it must be approved before the works.

Do I need shoring for a basement or deep excavation?

Where applicable, DDA requires shoring; we design and submit it.

Do pools in DDA areas need Dubai Municipality approval?

Yes, the Dubai Municipality Environment Department NOC is needed for pools in every area.

What documents does DDA need?

Title deed, owner ID, affection plan, the developer NOC, existing drawings, and proposed drawings with stamped calculations.

What is the difference between DDA and Dubai Municipality?

They cover different areas. DDA covers its master communities and free zones; Dubai Municipality covers most of mainland Dubai.

What happens after the works?

DDA inspection and the completion certificate close the permit.

What if DDA comments on my drawings?

We answer the comments and resubmit.

Do fit-outs in TECOM zones need DDA?

Yes, fit-out submissions in the TECOM zones go through the DDA portal.