DCM · Sewerage

DCM sewerage NOC: connecting to the community sewer

In DCM communities, a new or changed sewer connection is approved in stages on the Dubai Holding Community Management portal: design first, then construction, then inspection before discharge. We handle all three.

There are three sewerage NOCs on the portal. Design approves the drawings. Construction lets the contractor build the connection. Inspection, discharge and completion is the check before the property can discharge into the sewer. Connection works in the road reserve also need the ROW and RTA steps.

Stage 1Connection design
Stage 2Sewerage construction
Stage 3Inspection, discharge, completion
In the road reserveROW NOC and RTA too

When you need a sewerage NOC

  • New villa or building: A new connection to the community sewer
  • Changed connection: Moving or adding a connection
  • Larger works: Works that change the drainage layout
  • Road reserve: Connection works outside the plot
  • Inspection: Before discharge is allowed
  • Renewal: When construction runs longer

Documents you will need

  • Drainage layout and connection details (we prepare these)
  • Levels of the manholes and the connection
  • Site services information
  • Title deed and affection plan
  • Contractor trade licence

NOC types

The three sewerage NOCs

Applied for in this order.

NOCApproval routeGuides
Sewerage connection (design)
DCM
Drainage layout and connection to the community sewer. New or renewal.—
Sewerage construction
DCM
Building the connection. New or renewal.—
Sewerage connection (inspection / discharge / completion)
DCM
Inspection before discharge is allowed.—

How it works

How we get it done

1. Survey

Existing manholes, levels and services.

2. Design

Drainage layout and connection details.

3. Design NOC

Sewerage connection (design).

4. Construction NOC

Sewerage construction.

5. Build

By your contractor.

6. Inspection

Discharge and completion.

What owners ask us about

Common reasons for comments

  • Levels that do not work with the existing sewer
  • Existing services not shown
  • Discharge before inspection
  • Construction NOC expired

Need a sewer connection?

Get your sewerage NOCs

Send us three things on WhatsApp:

  1. Your community and plot number
  2. Photos of the manhole or connection point
  3. What you are building

We design the connection and handle the three DCM sewerage NOCs.

Questions

Questions

Is DCM the same as Dubai Holding Community Management?

Many owners and contractors still call it DCM. Today these NOCs are requested on the Dubai Holding Community Management NOC portal, and that is where we submit them.

Do I need a sewerage NOC for an extension or a new bathroom?

Only if the works add or change the connection to the community sewer. We check your drainage layout.

Do I need a sewerage NOC for a new villa?

Yes. A new connection goes through all three stages.

How do I connect to the sewer in a DCM community?

Get the sewerage connection (design) NOC, then the sewerage construction NOC, then the inspection / discharge / completion NOC before discharging.

What drawings are needed?

The drainage layout, the connection and manhole details, and the levels. We prepare them.

Who inspects the connection?

It is inspected under the inspection / discharge / completion NOC before discharge is allowed.

Can I discharge before the inspection?

No. Discharge is only allowed after the inspection.

Do I need a ROW NOC as well?

If the connection works are in the road reserve, yes, and the RTA NOC after it.

Can the sewerage construction NOC be renewed?

Yes, if construction runs longer.

Who can apply for a DCM NOC?

Only registered consultants and contractors can apply on the Dubai Holding Community Management NOC portal. Owners cannot apply themselves. We are registered and submit for our clients.