DCM site access NOC: before your contractor starts

In DCM communities, even a soil test or a topographic survey needs a site access NOC, and the contractor needs construction site access and hoarding NOCs before mobilization. Storing materials outside the plot needs a temporary site utilisation NOC.

There are separate site access NOCs for each stage of a project: studies first (soil investigation, topographic survey, traffic impact or environmental studies), then hoarding, construction site access, mobilization, and shoring and piling. Laydown outside the plot is its own NOC.

Before studiesSurvey and soil investigation access
Before worksHoarding and construction site access
LaydownTemporary site utilisation NOC
ApplicationsNew or renewal

Site access NOCs

  • Hoarding: Temporary site fence at the plot boundary
  • Site access: Construction site access
  • Mobilization: Setting up the site
  • Soil investigation: Access for soil tests
  • Shoring and piling: Access inside the plot limits
  • Studies: Topographic survey, traffic impact, environmental

Documents you will need

  • Site layout with hoarding and access (we prepare this)
  • Title deed and affection plan
  • Owner letter
  • Contractor or survey company trade licence
  • Planned start date and duration

NOC types

Site access NOC types

Pick the one for your stage of works.

NOCApproval routeGuides
Temporary site fence (hoarding) at plot boundary
DCM
Hoarding installed on the plot limits. New or renewal.RTA hoarding NOC
Temporary construction site access
DCM
Construction access to the plot. New or renewal.—
Mobilization
DCM
Setting up the site for works. New or renewal.—
Plot soil investigation site access
DCM
Access for soil tests. New or renewal.Soil test
Shoring and piling works site access (inside plot limits)
DCM
Access for shoring and piling rigs. New or renewal.Shoring permit
Topographic survey, traffic impact, environmental studies site access
DCM
Access for surveys and studies. New or renewal.Traffic Impact Study
Temporary site utilisation / fence laydown
DCM
Using land outside the plot for storage or laydown.—

How it works

How we get it done

1. Studies access

Soil investigation and surveys.

2. Design and permits

Drawings and approvals for the works.

3. Hoarding

Hoarding NOC at the plot boundary.

4. Site access

Construction site access and mobilization.

5. Piling

Shoring and piling access.

6. Laydown

If land outside the plot is needed.

What owners ask us about

Common reasons for comments

  • Hoarding outside the plot limits
  • Site works started before the access NOC
  • Laydown outside the plot without a NOC
  • NOC expired during the works

Starting work on site?

Get your site access NOCs

Send us three things on WhatsApp:

  1. Your community and plot number
  2. What stage the project is at
  3. Your contractor or survey company

We prepare the layouts and submit the DCM site access NOCs.

Questions

Questions

Is DCM the same as Dubai Holding Community Management?

Many owners and contractors still call it DCM. Today these NOCs are requested on the Dubai Holding Community Management NOC portal, and that is where we submit them.

Do I need a NOC for a topographic survey?

Yes. Topographic surveys, traffic impact studies and environmental studies have a site access NOC.

Do I need a NOC for a soil investigation?

Yes, the plot soil investigation site access NOC.

Do I need a NOC before my contractor starts in a DCM community?

Yes. The contractor needs the hoarding and construction site access NOCs, and the mobilization NOC to set up the site.

What are the hoarding rules on the plot boundary?

The hoarding NOC covers a temporary site fence installed on the plot limits. We prepare the layout.

Do I need site access for shoring and piling?

Yes, the shoring and piling works site access NOC, for work inside the plot limits.

Can I store materials on the land next to my plot?

Only with the temporary site utilisation / fence laydown NOC.

Can site access NOCs be renewed?

Yes, if the works run longer.

Do I still need the building permit?

Yes. Site access NOCs do not replace the building permit from the authority for your area.

Who can apply for a DCM NOC?

Only registered consultants and contractors can apply on the Dubai Holding Community Management NOC portal. Owners cannot apply themselves. We are registered and submit for our clients.