Al Furjan Plot Access NOC
A new driveway, second access, wider gate or kerb cut for a villa in Al Furjan needs plot access approval from Nakheel and RTA before any work at the road edge. We survey the plot, prepare DLTM drawings and handle the approvals.
The Approval Route in Al Furjan
RTA Access Design Study → Nakheel Plot Access, Curb Cut & Interlock NOC → RTA Construction NOC → RTA Sidewalk Modification Permit → works → deposit refund.
What you need to know
- Drawings That Get Accepted: Applications are returned when drawings are not in PDF plus AutoCAD DLTM format or do not match the RTA-approved design. Our drawings are prepared from a site survey and show the plot limit, kerb, interlock and tie-in clearly.
- Order of approvals: RTA access design study → developer plot access NOC → RTA construction NOC → sidewalk modification permit.
- DLTM drawings: developers such as Nakheel return drawings that are not PDF plus AutoCAD DLTM.
- Outside the plot limit: kerb, verge and interlock works are in the road reserve.
- No early works: concept approval alone does not allow works on site.
- Deposit refund: after the works are inspected and accepted.
Documents you will need
- Title deed and affection plan
- Owner passport and Emirates ID copy
- Survey-based drawings in PDF and AutoCAD DLTM
- RTA-approved access design (for the developer NOC)
At a glance
Al Furjan Plot Access NOC at a glance
Who does what, step by step.
| Who | Approval route | Guides |
|---|---|---|
| Structural engineer Step 1 | Surveys the plot and prepares access, kerb and interlock drawings in PDF and AutoCAD DLTM. | — |
| RTA Step 2 | Access design study (concept approval). | — |
| Nakheel Step 3 | Plot access, curb cut and interlock NOC where the community has one. | — |
| RTA Step 4 | Construction NOC, then the sidewalk modification permit. | — |
| RTA and developer Step 5 | Inspection after works and security deposit refund. | — |
How it works
How We Get Your Plot Access Approved
Site Survey & Plot Limits (DLTM)
RTA Access Design Study
Nakheel Plot Access NOC
RTA Construction NOC
RTA Sidewalk Modification Permit
Works, Handover & Deposit Refund
Who does what
Three parties, one route
Nakheel
Master developer of Al Furjan. Issues the NOC through its online portal.
Nakheel approvals →Trakhees
Issues the building permit for structural works and inspects at completion.
Trakhees approval →Structural Solutions
Prepares the drawings and stamped calculations and submits to Nakheel and Trakhees for you.
Talk to our engineers →Projects We Handle
- New Driveway
- Second Driveway
- Driveway Widening
- Kerb Cut
- Interlock Outside Plot
- Gate Relocation
Why applications come back
- Drawings that do not match the villa as it stands
- AutoCAD in DLTM coordinates not supplied where asked
- No stamped structural calculations
- Unapproved works already on the VSR
- Missing owner documents
Questions
Questions owners ask
Who approves plot access in Al Furjan?
RTA Access Design Study → Nakheel Plot Access, Curb Cut & Interlock NOC → RTA Construction NOC → RTA Sidewalk Modification Permit → works → deposit refund.
Do I need DLTM drawings?
Yes — PDF plus AutoCAD drawings in DLTM coordinates, prepared from a site survey.
Do you prepare the access drawings?
Yes — we survey the site and prepare access, kerb, interlock and tie-in drawings in AutoCAD (DLTM) and PDF.
Can works start before all approvals?
No — access, kerb and interlock works should start only after the RTA construction NOC and sidewalk modification permit are issued.
Who handles the submissions?
We prepare the drawings and handle the RTA and developer submissions as your consultant.