Maple · Dubai Hills townhouses

Maple Townhouse Main Door Relocation (Type 3C)

Maple townhouse main door relocation is allowed for Type 3C only. It counts within the 10% limit, with a 0.6 m offset from the edge of the slab.

Maple townhouse main door relocation is allowed for Type 3C only. The main door can be relocated by leaving a 0.6 m offset from the edge of the slab, and this is treated as an extension within the 10% allowable GFA. Other townhouse types cannot relocate the main door under Emaar’s guide. If you are not sure of your type, send us your unit number and any plans you have, and we will check. As with other works in Maple, this is subject to Emaar review.

Allowed forType 3C only
Offset0.6 m from slab edge
Counts inThe 10% limit

Emaar’s guide

Main door rules in Maple

From Emaar’s Maple Townhouses guide (April 2022). Emaar reviews every application.

ItemWhat the guide says
Allowed forType 3C only
Offset0.6 m from the edge of the slab
LimitCounts as an extension, within the 10% allowable GFA

Official sites: Emaar · Dubai Development Authority

Maple townhouse main door relocation: the rules

  • Check your type: Your plans show the unit type. Emaar provides as-built plans.
  • Shares the 10%: It uses part of the same additional area as an extension.
  • Matching finishes: Doors and finishes should match the townhouse.
  • Other types: Not allowed under the guide.

Documents you will need

  • Title deed and owner ID
  • Existing and proposed drawings and elevations
  • Detailed scope of works
  • Photos of the townhouse
  • Contractor or consultant licence
  • Building Completion Certificate

How it works

From idea to approval in Maple

1. Check

We check your idea against Emaar’s Maple guide and your plot.

2. Drawings

Drawings and stamped calculations, using the as-built plans Emaar provides.

3. Emaar NOC

We apply for you.

4. DDA permit

The building permit for structural works.

5. Works

Built as approved.

6. Completion

Emaar and DDA inspections, and the completion certificate.

Who does what

Who is involved

📐

Structural Solutions

Checks your idea, prepares the drawings and stamped calculations, and handles the Emaar NOC and DDA permit. We are a consultancy, not Emaar or DDA.

Maple townhouse rules →
🏘️

Emaar

Reviews the design and issues the NOC.

Emaar approvals →
🏛️

Dubai Development Authority (DDA)

Issues the building permit for structural works, after the Emaar NOC.

DDA approvals →

Why applications come back

  • Design does not follow Emaar’s Maple guide
  • Materials or colours do not match the townhouse
  • Neighbour NOC missing where it is needed
  • Works started before the NOC

Questions

Questions people ask

Can I move my main door?

Only on Type 3C, under Emaar’s guide.

How far can it move?

It leaves a 0.6 m offset from the edge of the slab.

Does it count as extra area?

Yes, within the 10%.

How do I know my type?

Your plans show it. Send us your unit number, and we will check.