Quick answer
Every Emaar villa needs an Emaar NOC first, but the building permit depends on the community. Emaar DM or DDA comes down to this: Emirates Living (The Springs, Meadows, Lakes, Emirates Hills, The Greens and The Views) goes to Dubai Municipality. Arabian Ranches, Dubai Hills Estate and The Valley go to DDA.
Last checked: November 2026. Official sources: Emaar · Dubai Municipality · DDA
Many owners and contractors assume that one developer means one authority. With Emaar that is not the case. Two villas built by the same developer can go to different authorities, and a submission to the wrong one wastes time.
Which authority applies to your community
| Community | Developer step | Building permit |
|---|---|---|
| The Springs | Emaar NOC | Dubai Municipality |
| The Meadows | Emaar NOC | Dubai Municipality |
| The Lakes | Emaar NOC | Dubai Municipality |
| Emirates Hills | Emaar NOC | Dubai Municipality |
| Arabian Ranches 1, 2 and 3 | Emaar NOC | DDA |
| Dubai Hills Estate | Emaar NOC | DDA |
| The Valley | Emaar NOC | DDA |
| Emaar South | Emaar NOC | Dubai South Authority, plus DCAA |
Emaar South is the exception many people miss: it is neither DM nor DDA. The full list of areas is in our community authority directory.
Dubai Hills sub-communities
Fairways, Hills Views and Majestic Villas are part of Dubai Hills Estate, so they follow Emaar and then DDA. See is Dubai Hills under DM, DDA or Trakhees.
What stays the same
- The NOC is applied for.
- Emaar provides villa plans to owners.
- Works start only after the building permit is issued.
- Structural works need stamped structural calculations.
- At the end, Emaar inspects, issues its clearance and releases the security deposit.
What changes
- Who issues the building permit: Dubai Municipality or DDA.
- The drawing format the authority expects.
- Who issues the completion certificate. See the DM completion certificate and the DDA completion certificate.
Apartments in Emaar buildings
Apartments follow a different route, starting with the building management NOC. For example, see merging apartments in Dubai.
Questions owners ask
Is The Springs under DM or DDA?
Dubai Municipality. All of Emirates Living goes through Emaar and then Dubai Municipality.
Is Emirates Hills under DDA?
No. Emirates Hills goes through Emaar and then Dubai Municipality.
Is Arabian Ranches under DM or DDA?
DDA. Arabian Ranches 1, 2 and 3 go through Emaar and then DDA.
Is Dubai Hills Estate under DM or DDA?
DDA, including Fairways, Hills Views and Majestic Villas.
Is Emaar South under DDA?
No. Emaar South goes through Emaar and then Dubai South Authority, plus DCAA.
Does the Emaar NOC replace the building permit?
No. The NOC is the developer step. The building permit comes from the authority, and works start only after it is issued.
Related service
Emaar approvals
We confirm the authority for your villa, prepare the drawings and calculations, and handle the Emaar NOC and the building permit.