RTA · Question

Do I need an RTA permit for a truck crane on the road?

Yes, when the truck crane stands on a public road or footpath, closes or narrows a lane, or swings its load over the road. The approval comes from RTA, with a lane closure or traffic diversion layout.

Yes. A truck or mobile crane that sets up on a public road or footpath, closes or narrows a lane, or swings its load over the road needs RTA approval before the lift. The application shows the crane position and outriggers, the swing radius, the closed area and how traffic is diverted. On roads inside some master communities, the master developer’s road closure NOC is needed as well. Structural Solutions prepares the drawings and handles the application.

Issued byRTA
Needed whenCrane uses, closes or swings over a public road
IncludesCrane position and traffic diversion layout

When you need an RTA crane permit

  • Truck crane on the road: The crane parks or sets its outriggers on a public road, lay-by or footpath.
  • Lane or road closure: A lane, the hard shoulder or the whole road is closed while the crane works.
  • Traffic diversion: Traffic is moved into another lane or onto another route around the lift.
  • Swinging over the road: A crane inside the plot swings its jib or load over the road or footpath.
  • Community roads: Inside some master communities, the master developer also approves the closure.

Documents you will need

  • Trade licence of the contractor or crane company
  • Title deed or affection plan of the site
  • Developer NOC where the road is a community road
  • Crane details: type, capacity and outrigger layout
  • Site survey and drawings, in DLTM coordinates where asked

By situation

Which RTA approval for which crane job

We confirm the exact approvals for your site and lift.

SituationApproval routeGuides
Truck crane parked on the road
RTA crane permit
Crane position, outriggers and the closed area.Road closure permit
One lane closed for the lift
RTA lane closure
Lane closure layout with signs and cones.Lane closure permit
Traffic moved around the crane
RTA road diversion
Traffic diversion layout.Road diversion permit
Crane or works on the footpath
RTA footpath closure
Safe pedestrian route around the works.Footpath closure permit
Lift on a community road
Developer NOC + RTA where needed
Master developer road closure NOC.Dubai Holding road closure NOC
DCM road closure NOC

How it works

How we get your RTA crane permit

1. Site check

We check the road, the plot limit, services and where the crane can stand.

2. Crane position plan

Crane, outriggers, swing radius and the load path, in DLTM where asked.

3. Closure and diversion layout

The lane or road to be closed and how traffic and pedestrians go around it.

4. Checks

Outrigger loads on the road, a slab or a basement roof are checked where needed.

5. Applications

Master developer NOC where the road is a community road, then the RTA application.

6. Lift and close-out

The lift is done as approved; the road is reopened and the approval closed.

Who does what

Who approves a crane on the road

🚚

RTA

Approves any use of a public road or footpath for the works: crane position, lane or road closure and the traffic diversion.

RTA approvals →
🏘️

Master developer

Some master communities manage their own internal roads and issue their own road closure NOC, for example Dubai Holding communities.

Community road closure NOC →
📐

Structural Solutions

We prepare the crane position plan, the closure and diversion layouts and the checks, and handle the application for you.

Talk to our engineers →

Lifts we prepare approvals for

  • Pools, AC units and chillers lifted into villas
  • Steel, pergolas and roof structures
  • Glass, cladding and façade panels
  • Precast, machinery and warehouse equipment
  • Generators and transformers

Why crane applications come back

  • Crane position or swing radius not shown against the road and plot limit
  • No traffic diversion or lane closure layout
  • Drawings not in DLTM coordinates where asked
  • Outrigger loads on the road or a slab not checked
  • Missing master developer NOC on a community road

Questions

Questions about RTA crane permits

Do I need an RTA permit to park a truck crane on the road?

Yes. When a truck or mobile crane stands on a public road or footpath, or closes or narrows a lane, RTA approval is needed before the lift, with a lane closure or traffic diversion layout.

My crane is inside the plot. Do I still need RTA approval?

If the jib or the load swings over a public road or footpath, yes. We check the crane position and swing radius against the plot limit to confirm.

Do mobile cranes and tower cranes both need it?

Any crane that uses, closes or swings over a public road needs the RTA approval for that use of the road.

What do you prepare for the application?

The crane position plan with outriggers and swing radius, the closure and traffic diversion layout, and load checks where the outriggers sit on the road or a slab.

What about roads inside a master community?

Some master communities manage their own roads and issue their own road closure NOC, for example Dubai Holding communities. We confirm whether the master developer, RTA or both approve your lift.

Can you handle the whole application?

Yes. We prepare the drawings and handle the master developer and RTA applications; the crane company and contractor carry out the lift as approved.