DCM site access NOC: before your contractor starts
In DCM communities, even a soil test or a topographic survey needs a site access NOC, and the contractor needs construction site access and hoarding NOCs before mobilization. Storing materials outside the plot needs a temporary site utilisation NOC.
There are separate site access NOCs for each stage of a project: studies first (soil investigation, topographic survey, traffic impact or environmental studies), then hoarding, construction site access, mobilization, and shoring and piling. Laydown outside the plot is its own NOC.

Official sources: Dubai Holding Community Management NOC portal · Roads and Transport Authority
Site access NOCs
- Hoarding: Temporary site fence at the plot boundary
- Site access: Construction site access
- Mobilization: Setting up the site
- Soil investigation: Access for soil tests
- Shoring and piling: Access inside the plot limits
- Studies: Topographic survey, traffic impact, environmental
Documents you will need
- Site layout with hoarding and access (we prepare this)
- Title deed and affection plan
- Owner letter
- Contractor or survey company trade licence
- Planned start date and duration
NOC types
Site access NOC types
Pick the one for your stage of works.
| NOC | Approval route | Guides |
|---|---|---|
| Temporary site fence (hoarding) at plot boundary DCM | Hoarding installed on the plot limits. New or renewal. | RTA hoarding NOC |
| Temporary construction site access DCM | Construction access to the plot. New or renewal. | — |
| Mobilization DCM | Setting up the site for works. New or renewal. | — |
| Plot soil investigation site access DCM | Access for soil tests. New or renewal. | Soil test |
| Shoring and piling works site access (inside plot limits) DCM | Access for shoring and piling rigs. New or renewal. | Shoring permit |
| Topographic survey, traffic impact, environmental studies site access DCM | Access for surveys and studies. New or renewal. | Traffic Impact Study |
| Temporary site utilisation / fence laydown DCM | Using land outside the plot for storage or laydown. | — |
How it works
How we get it done
1. Studies access
Soil investigation and surveys.
2. Design and permits
Drawings and approvals for the works.
3. Hoarding
Hoarding NOC at the plot boundary.
4. Site access
Construction site access and mobilization.
5. Piling
Shoring and piling access.
6. Laydown
If land outside the plot is needed.
What owners ask us about
- Right of way NOC
- Road closure and night works
- Shoring permit
- Demolition hoarding
Common reasons for comments
- Hoarding outside the plot limits
- Site works started before the access NOC
- Laydown outside the plot without a NOC
- NOC expired during the works
Starting work on site?
Get your site access NOCs
Send us three things on WhatsApp:
- Your community and plot number
- What stage the project is at
- Your contractor or survey company
We prepare the layouts and submit the DCM site access NOCs.
Questions
Questions
Is DCM the same as Dubai Holding Community Management?
Many owners and contractors still call it DCM. Today these NOCs are requested on the Dubai Holding Community Management NOC portal, and that is where we submit them.
Do I need a NOC for a topographic survey?
Yes. Topographic surveys, traffic impact studies and environmental studies have a site access NOC.
Do I need a NOC for a soil investigation?
Yes, the plot soil investigation site access NOC.
Do I need a NOC before my contractor starts in a DCM community?
Yes. The contractor needs the hoarding and construction site access NOCs, and the mobilization NOC to set up the site.
What are the hoarding rules on the plot boundary?
The hoarding NOC covers a temporary site fence installed on the plot limits. We prepare the layout.
Do I need site access for shoring and piling?
Yes, the shoring and piling works site access NOC, for work inside the plot limits.
Can I store materials on the land next to my plot?
Only with the temporary site utilisation / fence laydown NOC.
Can site access NOCs be renewed?
Yes, if the works run longer.
Do I still need the building permit?
Yes. Site access NOCs do not replace the building permit from the authority for your area.
Who can apply for a DCM NOC?
Only registered consultants and contractors can apply on the Dubai Holding Community Management NOC portal. Owners cannot apply themselves. We are registered and submit for our clients.