Dubai Holding site services information: utilities around your plot

Before designing a driveway, sewer connection or works in the road reserve in a Dubai Holding community, you need to know what services are already there. The Site Services Information request gives you that. We request it and use it in your drawings.

The short answer

Site Services Information is a request on the Dubai Holding Community Management NOC portal for the existing utilities and services around a plot. It is used before designing vehicle access, sewer connections and right of way works, so the design avoids clashes. Where the information is not enough, trial pits can confirm what is in the ground, which needs its own ROW NOC.

RequestSite Services Information
Used forDriveways, sewer, ROW works
Who appliesRegistered consultant or contractor
If unclearTrial pit NOC

Why you need it

  • Driveway design: Avoid cables and pipes under the new access
  • Sewer connection: Find the right connection point
  • ROW works: Plan excavation safely
  • Trial pits: Confirm services on site
  • As-built drawings: Combine with a survey of your plot
  • Fewer comments: Drawings that show existing services

Documents you will need

  • Title deed and affection plan
  • Plot location
  • Owner letter
  • Purpose of the request

NOC types

How it fits with other NOCs

Site Services Information comes first.

NOCApproval routeGuides
Site Services Information
Dubai Holding
Existing utilities around the plot.—
Trial pit
Dubai Holding, then RTA
Confirm services in the ground.—
Vehicle access design
Dubai Holding, then RTA
Uses the services information.—
Sewerage connection design
Dubai Holding
Uses the services information.—

How it works

How we get it done

1. Request

Site Services Information on the portal.

2. Review

We check the services around the plot.

3. Survey

Plot and road side survey.

4. Trial pits

If needed, with a trial pit NOC.

5. Design

Drawings that avoid clashes.

6. NOCs

Submit the works NOCs.

What owners ask us about

  • As-built survey
  • Vehicle access and gate level
  • Sewerage connection
  • Right of way NOC

Common reasons for comments

  • Design without existing services
  • Excavation without checking services
  • Missing trial pits where services are unclear

Planning works near the road?

Check the services first

Send us three things on WhatsApp:

  1. Your community and plot number
  2. Photos of the plot and road side
  3. What you plan to build

We request the site services information and design around it.

Questions

Questions

What is Dubai Holding Site Services Information?

A request on the Dubai Holding Community Management NOC portal for the existing utilities and services around a plot.

Why do I need it?

So the design for a driveway, sewer connection or ROW works avoids existing services.

Who can request it?

Registered consultants and contractors on the portal. We request it for you.

What if the information is not clear?

A trial pit, with its own ROW NOC, confirms what is in the ground.

Is it the same as as-built drawings of my villa?

No. It covers services around the plot. For drawings of your villa, see our as-built drawings service.

Do I need it for a new driveway?

We recommend it before any vehicle access design.