DSO and DCD Approval: Do I Need Both, and in What Order?
Yes. Every commercial fit-out change in Dubai Silicon Oasis needs Civil Defence (DCD) approval, after the building NOC and the DSO Authority (DIEZ) permit.
Yes, you need both. In Dubai Silicon Oasis every commercial fit-out change needs Dubai Civil Defence (DCD) approval for the fire safety, as well as the DSO Authority permit (DSO Authority is part of DIEZ). The order is: building management or landlord NOC, then the DSO Authority permit, then DCD approval of the fire safety drawings, then the works, then inspection and completion before the unit opens. Clinics add DHA, and restaurants add DM Food Safety.
What you need to know
- Every change: Even small layout or ceiling changes affect the fire safety.
- Order: Building NOC, DSO Authority permit, DCD, works, completion.
- Sprinklers and alarm: Moved devices are shown on the fire safety drawings.
- Inspection: DCD inspects before the unit opens.
- Clinics and restaurants: Add DHA or DM Food Safety.
Documents you will need
- Lease or title deed, and trade licence for businesses
- Building management or landlord NOC
- Existing or as-built drawings of the unit
- Proposed fit-out drawings, stamped by the consultant
- Fire safety drawings for Civil Defence
- Structural calculations where loads or openings change
By type of unit
The order of approvals in DSO
We confirm the route for your unit.
| Step | Approval route | Guides |
|---|---|---|
| 1. Building NOC Building management or landlord | First. | Building NOC |
| 2. DSO Authority permit Part of DIEZ | Fit-out or building permit. | DIEZ approval |
| 3. Civil Defence Fire safety drawings | Every commercial change. | Sprinklers and alarm |
| 4. Works To the approved drawings | No changes on site. | — |
| 5. Completion Inspections | Before opening. | Completion |
How it works
How we get your DSO approval
1. Review
The unit, the planned works and the drawings you have.
2. Drawings
Existing drawings, or we survey and redraw the unit.
3. Building NOC
From building management or the landlord.
4. DSO Authority
Fit-out or building permit, part of DIEZ.
5. Civil Defence
Fire safety drawings approved.
6. Works
Carried out to the approved drawings.
7. Completion
Inspection and completion before the unit opens.
Who does what
Who approves it in Dubai Silicon Oasis
Building management or landlord
Issues the NOC for the works in your unit. There is no developer NOC in DSO.
Building NOC →DSO Authority (DIEZ)
Issues the fit-out or building permit for works in Dubai Silicon Oasis.
DIEZ approval →Dubai Civil Defence
Approves the fire safety for every commercial fit-out change and inspects before completion.
DSO and DCD →Structural Solutions
Prepares the drawings and calculations and handles the submissions as consultant.
Talk to our engineers →What we prepare
- Fire safety drawings
- DCD submission and comments
Why DSO submissions get returned
- Building management or landlord NOC missing
- Drawings that do not match the unit on site
- Fire safety changes not shown for Civil Defence
- Structural changes without stamped calculations
- Works started before the permit
Questions
Questions tenants and owners ask
Do I need DCD approval for a fit-out in DSO?
Yes, every commercial fit-out change needs DCD approval.
Which comes first, DSO or DCD?
The building NOC, then the DSO Authority permit, then DCD.
Does a small change need DCD?
Yes, if it is a commercial fit-out change.
Who submits to DCD?
The consultant; we prepare and submit the fire safety drawings.
When can the unit open?
After the inspection and completion.