Nakheel · Al Furjan

Al Furjan Plot Access NOC

A new driveway, second access, wider gate or kerb cut for a villa in Al Furjan needs plot access approval from Nakheel and RTA before any work at the road edge. We survey the plot, prepare DLTM drawings and handle the approvals.

The Approval Route in Al Furjan

RTA Access Design Study → Nakheel Plot Access, Curb Cut & Interlock NOC → RTA Construction NOC → RTA Sidewalk Modification Permit → works → deposit refund.

RTA Design StudyFirst step
DLTM DrawingsPDF + AutoCAD
Sidewalk PermitBefore works

What you need to know

  • Drawings That Get Accepted: Applications are returned when drawings are not in PDF plus AutoCAD DLTM format or do not match the RTA-approved design. Our drawings are prepared from a site survey and show the plot limit, kerb, interlock and tie-in clearly.
  • Order of approvals: RTA access design study → developer plot access NOC → RTA construction NOC → sidewalk modification permit.
  • DLTM drawings: developers such as Nakheel return drawings that are not PDF plus AutoCAD DLTM.
  • Outside the plot limit: kerb, verge and interlock works are in the road reserve.
  • No early works: concept approval alone does not allow works on site.
  • Deposit refund: after the works are inspected and accepted.

Documents you will need

  • Title deed and affection plan
  • Owner passport and Emirates ID copy
  • Survey-based drawings in PDF and AutoCAD DLTM
  • RTA-approved access design (for the developer NOC)

At a glance

Al Furjan Plot Access NOC at a glance

Who does what, step by step.

WhoApproval routeGuides
Structural engineer
Step 1
Surveys the plot and prepares access, kerb and interlock drawings in PDF and AutoCAD DLTM.—
RTA
Step 2
Access design study (concept approval).—
Nakheel
Step 3
Plot access, curb cut and interlock NOC where the community has one.—
RTA
Step 4
Construction NOC, then the sidewalk modification permit.—
RTA and developer
Step 5
Inspection after works and security deposit refund.—

How it works

How We Get Your Plot Access Approved

Site Survey & Plot Limits (DLTM)

RTA Access Design Study

Nakheel Plot Access NOC

RTA Construction NOC

RTA Sidewalk Modification Permit

Works, Handover & Deposit Refund

Who does what

Three parties, one route

🏘️

Nakheel

Master developer of Al Furjan. Issues the NOC through its online portal.

Nakheel approvals →
🏛️

Trakhees

Issues the building permit for structural works and inspects at completion.

Trakhees approval →
📐

Structural Solutions

Prepares the drawings and stamped calculations and submits to Nakheel and Trakhees for you.

Talk to our engineers →

Projects We Handle

  • New Driveway
  • Second Driveway
  • Driveway Widening
  • Kerb Cut
  • Interlock Outside Plot
  • Gate Relocation

Why applications come back

  • Drawings that do not match the villa as it stands
  • AutoCAD in DLTM coordinates not supplied where asked
  • No stamped structural calculations
  • Unapproved works already on the VSR
  • Missing owner documents

Questions

Questions owners ask

Who approves plot access in Al Furjan?

RTA Access Design Study → Nakheel Plot Access, Curb Cut & Interlock NOC → RTA Construction NOC → RTA Sidewalk Modification Permit → works → deposit refund.

Do I need DLTM drawings?

Yes — PDF plus AutoCAD drawings in DLTM coordinates, prepared from a site survey.

Do you prepare the access drawings?

Yes — we survey the site and prepare access, kerb, interlock and tie-in drawings in AutoCAD (DLTM) and PDF.

Can works start before all approvals?

No — access, kerb and interlock works should start only after the RTA construction NOC and sidewalk modification permit are issued.

Who handles the submissions?

We prepare the drawings and handle the RTA and developer submissions as your consultant.