Unpermitted Mezzanine in a DIP Warehouse: Retrospective Approval
A mezzanine built in a DIP warehouse without a permit needs a retrospective approval.
A mezzanine must be approved before it is built. In DIP, one built without a permit needs a retrospective approval: survey and as-built drawings, a structural assessment with strengthening where needed, the landlord and PID/DIP NOCs, the Dubai Municipality approval, the approved steel contractor stamp and Dubai Civil Defence approval.
What you need to know
- Survey: As-built drawings.
- Assessment: Structure and slab.
- NOCs: Landlord and PID/DIP.
- Approvals: DM, steel stamp and DCD.
Documents you will need
- Trade licence and tenancy contract, or title deed for owners
- Landlord, building management or master developer NOC
- Existing or as-built drawings of the unit or villa
- Mezzanine drawings with stamped structural calculations
- Fire safety drawings for Civil Defence
By situation
Steps
We confirm the route for your building and area.
| Step | Approval route | Guides |
|---|---|---|
| Survey As-built drawings | First. | — |
| Assessment Stamped calculations | Strengthening if needed. | Calculations |
| Approvals PID/DIP NOC, DM, DCD | Retrospective. | DIP permit |
How it works
How we get your mezzanine approved
1. Site and slab review
The unit, the existing slab and columns, and what the mezzanine is for.
2. Existing drawings
From the landlord, developer or authority; if missing or out of date, we survey and draw as built.
3. Design and calculations
Mezzanine drawings, steel design and stamped structural calculations, with the added floor area shown.
4. NOC
Landlord, building management or master developer NOC.
5. Permit and Civil Defence
The authority for the area approves the structure; the approved steel contractor stamps the steel; DCD approves fire safety.
6. Build, inspect, complete
The mezzanine is built as approved, inspected, and the completion certificate is issued.
Who does what
Who approves a mezzanine
Landlord or developer
Gives the NOC for the mezzanine. It comes first.
Authority for the area
Dubai Municipality, DDA, Trakhees, DSO Authority, Dubai South Authority or DMCC approves the structure with stamped calculations.
Who approves? →Approved steel contractor
A steel mezzanine needs the stamp of an approved steel contractor (also called a steel specialist).
Steel contractor stamp →Dubai Civil Defence
Every mezzanine needs DCD approval for fire safety and escape.
What we prepare
- Survey and as-built drawings
- Structural assessment
Why mezzanine submissions get returned
- Mezzanine built before approval
- No landlord or developer NOC
- Drawings that do not match the unit as built
- Slab and columns not checked for the new loads
- Steel without the approved steel contractor stamp
- Added floor area not shown
- No Civil Defence fire safety drawings
Questions
Questions owners and tenants ask
Can an unpermitted mezzanine in DIP be approved?
It needs a retrospective approval; the authority decides.
Who approves it?
Dubai Municipality, after the PID/DIP NOC, with Civil Defence.