DIP Mezzanine Permit: PID/DIP NOC and Dubai Municipality
A mezzanine in a Dubai Investments Park warehouse needs the master developer NOC and a Dubai Municipality permit.
In Dubai Investments Park, a warehouse mezzanine needs the landlord NOC and the master developer (PID/DIP) NOC, then a Dubai Municipality building permit with stamped structural calculations, the approved steel contractor stamp for the steel, and Dubai Civil Defence approval. DM issues the completion after the works. The mezzanine counts as added floor area.
What you need to know
- Landlord and master developer: Both NOCs first.
- DM permit: With stamped calculations.
- Steel: Approved steel contractor stamp.
- Civil Defence: Every mezzanine.
Documents you will need
- Trade licence and tenancy contract, or title deed for owners
- Landlord, building management or master developer NOC
- Existing or as-built drawings of the unit or villa
- Mezzanine drawings with stamped structural calculations
- Fire safety drawings for Civil Defence
By situation
Route in DIP
We confirm the route for your building and area.
| Step | Approval route | Guides |
|---|---|---|
| 1. NOCs Landlord and PID/DIP | First. | — |
| 2. DM permit Dubai Municipality | Stamped calculations. | Calculations |
| 3. Steel and DCD Steel contractor, DCD | Before building. | — |
| Built already Retrospective approval | DIP route. | Unpermitted |
How it works
How we get your mezzanine approved
1. Site and slab review
The unit, the existing slab and columns, and what the mezzanine is for.
2. Existing drawings
From the landlord, developer or authority; if missing or out of date, we survey and draw as built.
3. Design and calculations
Mezzanine drawings, steel design and stamped structural calculations, with the added floor area shown.
4. NOC
Landlord, building management or master developer NOC.
5. Permit and Civil Defence
The authority for the area approves the structure; the approved steel contractor stamps the steel; DCD approves fire safety.
6. Build, inspect, complete
The mezzanine is built as approved, inspected, and the completion certificate is issued.
Who does what
Who approves a mezzanine
Landlord or developer
Gives the NOC for the mezzanine. It comes first.
Authority for the area
Dubai Municipality, DDA, Trakhees, DSO Authority, Dubai South Authority or DMCC approves the structure with stamped calculations.
Who approves? →Approved steel contractor
A steel mezzanine needs the stamp of an approved steel contractor (also called a steel specialist).
Steel contractor stamp →Dubai Civil Defence
Every mezzanine needs DCD approval for fire safety and escape.
What we prepare
- Drawings and stamped calculations
- NOC, DM and DCD submissions
Why mezzanine submissions get returned
- Mezzanine built before approval
- No landlord or developer NOC
- Drawings that do not match the unit as built
- Slab and columns not checked for the new loads
- Steel without the approved steel contractor stamp
- Added floor area not shown
- No Civil Defence fire safety drawings
Questions
Questions owners and tenants ask
Who approves a mezzanine in DIP?
Dubai Municipality, after the landlord and PID/DIP NOCs.
Is Civil Defence needed?
Yes.
Does it count as floor area?
Yes.
Related guides
