Light Pole in Front of My Driveway: Can It Be Moved?

A street light pole right where your new or wider driveway should be is common. It can often be moved, with RTA approval, as part of the access approval.

The short answer

Yes, often. The pole is an RTA asset, so it moves only with an RTA relocation approval. We survey the frontage, show the existing pole, the new position and the cable route in DLTM drawings, and apply for the relocation together with the driveway or gate access approval. In master communities the developer plot access NOC comes first.

Approved byRTA
Applied withThe driveway access approval
DrawingsSurvey-based, in DLTM

What you need to know

  • Moving, not removing: RTA approves a new position for the pole and its cable.
  • Gates and parking access: The same applies to a wider gate or a new parking access.
  • Order of approvals: Access Design Study, developer NOC where applicable, then the RTA construction NOC with the relocation.
  • Before works: The pole stays until the approval is issued.

Documents you will need

  • Title deed or affection plan
  • Owner Emirates ID or passport, or company documents
  • Site survey and drawings in DLTM coordinates
  • Developer NOC in a master community
  • Photos of the road side

By situation

Your situation

We confirm the route for your plot.

SituationApproval routeGuides
New driveway
Relocation plus access
Design the access around the new pole position.New villa driveway
Wider driveway or gate
Relocation plus access
Widening that reaches the pole.Driveway NOC
Second driveway
Relocation plus access
A second access point.Second driveway
Commercial or parking access
Relocation plus vehicle access
Plots with car or truck access.Vehicle access

How it works

How it works

1. Photos and plot details

We check the frontage and the pole.

2. Site survey

Pole, cable, kerb and plot limit.

3. Access and relocation drawings

In DLTM coordinates.

4. Developer NOC

Where there is a master developer.

5. RTA approval

Access and relocation together.

6. Works and inspection

Then the deposit is returned.

Who does what

Who approves it

🛣️

RTA

Reviews the drawings, issues the NOC or permit for works affecting the road and inspects the works.

RTA approvals →
🏘️

Master developer

In developer communities, its NOC comes before the RTA application.

Developer NOC first →
📐

Structural Solutions

Surveys the site, prepares the DLTM drawings and handles the applications for you.

Talk to our engineers →

Why RTA applications come back

  • Pole and cable not surveyed
  • New pole position conflicts with the access
  • Drawings not in DLTM coordinates
  • Developer NOC missing

Questions

Questions owners ask

Can I move the pole myself?

No. It is an RTA asset and moves only with RTA approval.

Is it a separate application?

The relocation is applied for together with the driveway or gate access approval.

Does this apply to a wider gate?

Yes. Any access change that reaches the pole follows the same route.

What do you need from me to start?

Photos of the frontage and the title deed or affection plan.