Kerb & Sidewalk Reinstatement Design Dubai
When a kerb is cut or a footpath is opened for an access, it must be reinstated to RTA standards. We prepare the reinstatement design and details as part of the access approval package.
What Is Reinstated
Kerbs, footpath paving, verges, edge restraints and any disturbed road surface — matched to the existing levels and materials.
What you need to know
- Linked to the Deposit: Proper reinstatement is checked before the works are accepted and the security deposit is refunded.
- Order of approvals: RTA access design study → developer plot access NOC → RTA construction NOC → sidewalk modification permit.
- DLTM drawings: Developers such as Nakheel return drawings that are not PDF plus AutoCAD DLTM.
- Outside the plot limit: Kerb, verge and interlock works are in the road reserve.
- No early works: Concept approval alone does not allow works on site.
- Deposit refund: After the works are inspected and accepted.
Documents you will need
- Title deed and affection plan
- Owner passport and Emirates ID copy
- Survey-based drawings in PDF and AutoCAD DLTM
- RTA-approved access design (for the developer NOC)
At a glance
Kerb & Sidewalk Reinstatement Design Dubai at a glance
Who does what, step by step.
| Who | Approval route | Guides |
|---|---|---|
| Structural engineer Step 1 | Surveys the plot and prepares access, kerb and interlock drawings in PDF and AutoCAD DLTM. | — |
| RTA Step 2 | Access design study (concept approval). | — |
| Master developer Step 3 | Plot access, curb cut and interlock NOC where the community has one. | — |
| RTA Step 4 | Construction NOC, then the sidewalk modification permit. | — |
| RTA and developer Step 5 | Inspection after works and security deposit refund. | — |
How it works
How We Get Your Plot Access Approved
Site Survey & Plot Limits (DLTM)
RTA Access Design Study
Developer Plot Access NOC
RTA Construction NOC
RTA Sidewalk Modification Permit
Works, Handover & Deposit Refund
Who does what
Who approves access works
RTA
Reviews the Access Design Study, then issues the Construction NOC and the Sidewalk Modification Permit, and inspects the works.
RTA approvals →Master developer
In communities such as Nakheel, Emaar or Dubai Holding areas, its plot access NOC comes before the RTA permit.
Developer NOC first →Structural Solutions
Surveys the site, prepares the DLTM drawings and handles the applications for you.
Talk to our engineers →Projects We Handle
- Kerb Reinstatement
- Footpath Reinstatement
- Verge Reinstatement
- Road Edge Repair
- Driveway Closure
- Access Relocation
Why applications come back
- Drawings not in AutoCAD DLTM coordinates
- Works outside the plot limit not shown against a site survey
- Developer plot access NOC missing in a master community
- Works started on concept approval only
- Kerb and footpath reinstatement not detailed
Questions
Questions owners ask
Who reinstates the sidewalk?
The applicant’s contractor, to the approved details.
Does reinstatement affect the deposit refund?
Yes — works are inspected before the deposit is refunded.
Do you prepare the access drawings?
Yes — we survey the site and prepare access, kerb, interlock and tie-in drawings in AutoCAD (DLTM) and PDF.
Can works start before all approvals?
No — access, kerb and interlock works should start only after the RTA construction NOC and sidewalk modification permit are issued.