How do I get a DCD completion certificate?
After the fire safety works are finished as approved, the consultant requests the DCD final inspection. DCD checks sprinklers, alarms, exits and other fire safety works against the approved drawings, then gives its final approval before the building completion.
DCD approval has two parts: approval of the fire safety drawings before the works, and a final inspection after them. The works must match the DCD-approved drawings, gas works must be done by a DCD-approved third party, and as-built fire safety drawings are prepared for the inspection.
What DCD checks
- Sprinklers and detectors: Positions match the approved drawings and the ceiling.
- Alarms and exits: Alarm system, exits and signage.
- Gas works: Done by a DCD-approved third party.
- As-built: Drawings that match what was built.
Documents you will need
- Trade licence and tenancy contract (Ejari)
- Landlord or building management NOC
- Fit-out drawings and stamped calculations
- Fire safety drawings
- Photos of the unit
Who does what
Step by step
The order can vary by community and authority; we confirm it for your project.
| Step | Approval route | Guides |
|---|---|---|
| Approved drawings DCD | Fire safety drawings approved before works. | DCD approvals |
| Works Contractor | Built to the approved drawings. | — |
| As-built drawings Consultant | Prepared for the inspection. | As-built drawings |
| Final inspection DCD | Inspection and final approval. | DCD final inspection |
Questions
Related questions
When is the DCD final inspection?
After the fire safety works are finished.
What if the inspection fails?
The comments are fixed and a re-inspection is requested.
Who does gas works?
A DCD-approved third party.
Is DCD separate from the building completion?
Yes, DCD approves fire safety; the building authority closes the permit.
What does Structural Solutions do?
Drawings, DCD submissions and coordination of the final inspection.