How do I apply for a DDA building permit?

Through an approved consultant, after the developer or building management NOC. The consultant submits the drawings and stamped calculations to DDA, answers comments, and handles inspection and the completion certificate.

In DDA communities such as Arabian Ranches, Dubai Hills, Business Bay and the TECOM zones, the developer NOC comes first, for example the Emaar NOC. An approved consultant then submits to DDA. The DDA building permit is about AED 1,500 to 3,000. Fire safety changes also need DCD, and pools need the DM Environment Department NOC.

Who appliesAn approved consultant
FirstThe developer NOC
DDA permitAbout AED 1,500 to 3,000

What to know before you apply

  • Approved consultant: Only an approved consultant can submit to DDA.
  • Developer NOC: Always first in DDA communities.
  • Other approvals: DCD for fire safety, DM for pools and food outlets.
  • Completion: Inspection and completion certificate after the works.

Documents you will need

  • Title deed and owner ID
  • Affection plan for the plot
  • Developer NOC (where the community has a developer)
  • Drawings and stamped structural calculations
  • Photos of the area

Who does what

Step by step

The order can vary by community and authority; we confirm it for your project.

StepApproval routeGuides
Developer NOC
Developer or building management
For example Emaar.Developer approvals
Design
Consultant
Drawings and stamped calculations.—
DDA submission
Consultant
Submitted by the consultant, with comments answered.DDA approvals
Completion
DDA and developer
Final inspections and completion certificate.DDA completion

Official fees

DDA permit fees and developer NOC fees

ItemAmountNote
DDA building permitAbout AED 1,500 to 3,000Varies with the works
Developer NOCSet by the developerPaid to the developer before the DDA submission
Emaar NOC (example)AED 2,000Includes the AED 500 submission fee
Emaar security depositAED 10,000Refundable after the works are completed and cleared

Official fees as of November 2026. DDA and the developers set these and can change them. Our engineering fee is separate and quoted after we review your project. Full DDA approval guide

Questions

Related questions

Can I apply to DDA myself?

No, submissions must be made by an approved consultant.

Do I need a developer NOC first?

Yes, in DDA communities the developer NOC comes first.

Which communities are under DDA?

For example Arabian Ranches, Dubai Hills, The Valley, Business Bay, Dubai Marina, Mudon, DAMAC Hills and the TECOM zones.

Do pools need anything extra?

Yes, the DM Environment Department pool NOC.

What does Structural Solutions do?

We handle the NOC, the DDA submission as approved consultant and completion.