Dubai Holding NOC portal: every NOC type explained

Dubai Holding Community Management issues NOCs for works in its communities through an online NOC portal. Only registered consultants and contractors can apply. We are registered, so we choose the right NOC, prepare the drawings and submit for you.

The short answer

The Dubai Holding Community Management NOC portal groups its NOCs into works in the right of way, road closure and traffic diversion, sewerage works, vehicle access, temporary construction access and fencing, temporary site utilisation, night works, the ROW work completion certificate and site services information. Each NOC has its own form and documents, and most are applied for as new, renewal or revision. For works on the road side, an RTA NOC follows. Building works on the plot also need the permit from the authority for your area.

Issued byDubai Holding Community Management
Who appliesRegistered consultant or contractor
ApplicationsNew, renewal or revision
Road-side worksRTA NOC after

The NOC groups on the portal

  • Right of way: Excavation, cables, pipes, dewatering, crossings
  • Road closure: Traffic diversion and night works
  • Sewerage: Design, construction, inspection and discharge
  • Vehicle access: Gate level, driveway design and completion
  • Site access: Hoarding, mobilization, surveys, piling
  • Site services: Existing utilities around your plot

Documents you will need

  • Title deed and affection plan
  • Owner letter or NOC for the works
  • Drawings for the works (we prepare these)
  • Contractor trade licence
  • Planned start date and duration of the works

NOC types

Which Dubai Holding NOC fits your works

Find your works, then read the guide for that NOC group.

NOCApproval routeGuides
Works in the road reserve
Dubai Holding, then RTA
Excavation, shoring, cables, pipes, dewatering, crossings, landscaping, trial pits.—
Closing a road or lane
Dubai Holding, then RTA
Road closure, traffic diversion and night works.—
Sewer connection
Dubai Holding
Design, construction, inspection and discharge.—
Driveway or gate
Dubai Holding, then RTA
Gate level and vehicle access design, construction and completion.—
Starting work on site
Dubai Holding
Hoarding, site access, mobilization, surveys, piling and laydown.—
Existing utilities
Dubai Holding
Information on services around the plot before design.—

How it works

How we get it done

1. Tell us the works

What, where and when.

2. Choose the NOC

The right group and type on the portal.

3. Drawings

Survey and drawings for that NOC.

4. Submit

On the portal, as your registered consultant.

5. Comments and NOC

We answer comments until it is issued.

6. Next approvals

RTA and the authority permit where needed.

What owners ask us about

  • Right of way NOC
  • Vehicle access and gate level
  • Sewerage connection
  • Construction site access
  • Road closure and night works

Common reasons for comments

  • Wrong NOC type selected
  • Drawings without existing services or levels
  • NOC expired before the works finished
  • Works started before the NOC was issued

Need a Dubai Holding NOC?

Get the right NOC first time

Send us three things on WhatsApp:

  1. Your community and plot number
  2. Photos of the area
  3. What you want to do

We choose the NOC, prepare the drawings and submit on the portal.

Questions

Questions

What is the Dubai Holding NOC portal?

The online portal of Dubai Holding Community Management where registered consultants and contractors apply for NOCs for works in its communities.

Who can apply for a Dubai Holding NOC?

Only registered consultants and contractors can apply on the Dubai Holding Community Management NOC portal. Owners cannot apply themselves. We are registered and submit for our clients.

Which Dubai Holding NOC do I need?

It depends on where the works are. Works in the road reserve need a right of way NOC, closing a road needs a road closure NOC, a sewer connection needs a sewerage NOC, a new driveway or gate needs a vehicle access NOC, and starting work on site needs a site access NOC. We check and choose the right one.

What is the difference between new, renewal and revision?

New is the first application. Renewal extends a NOC when the works run longer. Revision changes an approved NOC when the design or scope changes.

Do I also need an RTA NOC?

Yes, for works on the road side. The RTA NOC follows the Dubai Holding NOC.

Does the Dubai Holding NOC replace the building permit?

No. If you are also building or changing anything on the plot, you still need the building permit from the authority for your area. We check what applies to your works.

What documents does the Dubai Holding NOC portal ask for?

Usually the title deed and affection plan, an owner letter, the drawings for the works, the contractor trade licence and the planned dates. Each NOC type has its own list.

How long is a Dubai Holding NOC valid?

Each NOC covers a set period for the works. If the works run longer, apply for a renewal before it expires.

What is the ROW Work Completion Certificate?

The certificate issued after works in the right of way are finished and inspected.

What is Site Services Information?

Information on the existing utilities and services around your plot, used before design or digging.

Can works start before the NOC is issued?

No. Works should only start once the NOC is issued and the conditions are met.

Do you submit Dubai Holding NOCs for clients?

Yes. We prepare the drawings, submit on the portal, answer the comments and follow up to the completion certificate.