JVC · Question · Updated November 2026

Who Approves Unit Splitting in JVC?

Owners in JVC often expect Dubai Municipality to approve a shop split. In JVC it is a chain of five parties, and the order matters.

In JVC, a unit split is approved by five parties in order: the building owner or developer (NOC), Nakheel (NOC), Trakhees CED (works approval), Dubai Civil Defence (layout update) and the Dubai Land Department (title deed split, based on DLD-registered surveyor plans). Dubai Municipality is not part of the JVC route. We take the file through all five.

PartiesFive, in order
Not involvedDubai Municipality
Last stepDLD title deed split

Who does what

Who approves what in a JVC unit split

PartyRole
Building owner or developerAgrees to the split in the building
NakheelMaster developer NOC
Trakhees (CED)Approves the works
Dubai Civil DefenceApproves the updated layout
Dubai Land DepartmentSplits the title deed

Official sites: Trakhees | Dubai Civil Defence | Dubai Land Department

What you need to know

  • Five parties, in order.
  • Trakhees, not DM.
  • DCD for the layout.
  • DLD for the deeds.

Documents you will need

  • Building name and unit
  • Title deed

How it works

The approval order in JVC

1. Building

NOC.

2. Nakheel

NOC.

3. Trakhees

Works.

4. DCD

Layout.

5. Surveyor

Plans.

6. DLD

Deeds.

Questions

JVC approvals: questions

Does Dubai Municipality approve splits in JVC?

No. JVC works go to Trakhees after the Nakheel NOC.

What comes first?

The building owner or developer NOC, then Nakheel.

Who handles DLD?

We do. See JVC retail unit split for the full JVC route.

Who can help?

Structural Solutions takes JVC unit splits through all five parties. Contact our engineering team on WhatsApp or call us directly on +971 55 339 4451.