Mall fit-out approvals in Dubai depend on the mall. Dubai Outlet Mall needs the mall approval and Civil Defence. Dubai Hills Mall goes from mall community management to DDA, plus Civil Defence. Nakheel malls go from Nakheel community management to Trakhees, plus Civil Defence. Every commercial fit-out change needs Dubai Civil Defence approval.
Last checked: November 2026. Official sources: DDA · Trakhees · Dubai Civil Defence
This guide is for the three people who usually ask about a mall fit-out: the fit-out contractor, the tenant and the brand. The first question is always the same: which mall?
The route by mall
| Mall | First approval | Authority | Civil Defence |
|---|---|---|---|
| Dubai Outlet Mall | Mall approval | — | Required |
| Dubai Hills Mall | Mall community management | DDA | Required |
| Nakheel malls | Nakheel community management | Trakhees | Required |
For other malls, the route is confirmed for each project. Send us the mall name and we will check it.
Is the mall approval enough?
Usually not. Every commercial fit-out change, including partitions, ceilings and decoration updates, needs DCD approval, a DCD final inspection and a completion certificate. See is mall approval enough and do partition changes need approval.
Consultant stamp
At Dubai Outlet Mall, a consultant stamp is needed on the MEP, fire and architectural partition-change drawings. See the Dubai Outlet Mall consultant stamp and which drawings the mall needs.
Who applies
The contractor, the tenant or the brand can start the process. See who gets the approval.
Extra items to check
- DEWA: it depends on the case, the area and any load increase. Most mall shops do not need it. See DEWA for a mall shop.
- Gas: the approved LPG or gas provider needs its own approval. With electric cooking only, an undertaking letter goes to DCD.
- Restaurants: see food safety approval in a mall.
- Documents: see mall fit-out documents.
Before you open
The DCD final inspection is needed before opening. Do not start works before the mall approves: see can I start before the mall approves.
Questions tenants and contractors ask
Does every mall follow the same approval route?
No. It depends on the mall. Dubai Outlet Mall, Dubai Hills Mall and Nakheel malls all differ.
Does a shop in a mall need Civil Defence approval?
Yes. Every commercial fit-out change needs DCD approval, a DCD final inspection and a completion certificate.
Who approves fit-outs in Dubai Hills Mall?
Mall community management first, then DDA, plus DCD.
Who approves fit-outs in Nakheel malls?
Nakheel community management first, then Trakhees, plus DCD.
Do you prepare MEP drawings for mall shops?
Yes. We prepare MEP design and calculations. We do not provide BOQs or tendering.
Does a mall shop need DEWA approval?
It depends on the case, the area and any load increase. Most mall shops do not need it.