RTA · Plot access

Can I Start Interlock Works With Only Concept Approval?

No. The RTA concept approval (access design study) only accepts the design. Interlock, kerb and access works in the road reserve can start only after the developer NOC, the RTA construction NOC and the sidewalk modification permit.

What Happens If You Start Early

Works can be stopped, and you may be asked to remove them and reinstate the sidewalk.

First stepRTA Access Design Study
Developer NOCWhere the community has a master developer
DrawingsAutoCAD in DLTM coordinates

What you need to know

  • The Right Order: Concept approval → developer NOC → construction NOC → sidewalk modification permit → works.
  • Order of approvals: RTA access design study → developer plot access NOC → RTA construction NOC → sidewalk modification permit.
  • DLTM drawings: Developers such as Nakheel return drawings that are not PDF plus AutoCAD DLTM.
  • Outside the plot limit: Kerb, verge and interlock works are in the road reserve.
  • No early works: Concept approval alone does not allow works on site.
  • Deposit refund: After the works are inspected and accepted.

Documents you will need

  • Title deed and affection plan
  • Owner passport and Emirates ID copy
  • Survey-based drawings in PDF and AutoCAD DLTM
  • RTA-approved access design (for the developer NOC)

At a glance

Step by step

Who does what, step by step.

WhoApproval routeGuides
Structural engineer
Step 1
Surveys the plot and prepares access, kerb and interlock drawings in PDF and AutoCAD DLTM.—
RTA
Step 2
Access design study (concept approval).—
Master developer
Step 3
Plot access, curb cut and interlock NOC where the community has one.—
RTA
Step 4
Construction NOC, then the sidewalk modification permit.—
RTA and developer
Step 5
Inspection after works and security deposit refund.—

How it works

How We Get Your Plot Access Approved

Site Survey & Plot Limits (DLTM)

RTA Access Design Study

Developer Plot Access NOC

RTA Construction NOC

RTA Sidewalk Modification Permit

Works, Handover & Deposit Refund

Who does what

Who approves access works

🛣️

RTA

Reviews the Access Design Study, then issues the Construction NOC and the Sidewalk Modification Permit, and inspects the works.

RTA approvals →
🏘️

Master developer

In communities such as Nakheel, Emaar or Dubai Holding areas, its plot access NOC comes before the RTA permit.

Developer NOC first →
📐

Structural Solutions

Surveys the site, prepares the DLTM drawings and handles the applications for you.

Talk to our engineers →

Projects We Handle

  • Interlock
  • Kerb Cut
  • Driveway Apron
  • Footpath
  • Gate Area
  • Access Widening

Why applications come back

  • Drawings not in AutoCAD DLTM coordinates
  • Works outside the plot limit not shown against a site survey
  • Developer plot access NOC missing in a master community
  • Works started on concept approval only
  • Kerb and footpath reinstatement not detailed

Questions

Questions owners ask

Can I start with concept approval?

No.

What do I need before starting?

The developer NOC, RTA construction NOC and sidewalk modification permit.

Do you prepare the access drawings?

Yes — we survey the site and prepare access, kerb, interlock and tie-in drawings in AutoCAD (DLTM) and PDF.

Can works start before all approvals?

No — access, kerb and interlock works should start only after the RTA construction NOC and sidewalk modification permit are issued.