How do I apply for a Trakhees permit?
Through an approved consultant, after the developer NOC: the Nakheel NOC through the Nakheel online portal, or the JGE NOC through the wasl app. The consultant then submits the drawings and stamped calculations to Trakhees and handles inspection and completion.
The short answer
Trakhees approves building works in Nakheel communities such as Palm Jumeirah, Jumeirah Park, JVC and Al Furjan, in Jumeirah Golf Estates and in JAFZA. The developer NOC comes first, then an approved consultant submits to Trakhees CED. Fire safety changes need DCD, and pools need the DM Environment Department NOC.
What to know before you apply
- Approved consultant: Submissions to Trakhees must be made by an approved consultant.
- Developer NOC: Nakheel online portal or the wasl app.
- VSR: Unapproved works flagged in a Nakheel VSR should be fixed first.
- Completion: Inspection and completion certificate.
Documents you will need
- Title deed and owner ID
- Affection plan for the plot
- Developer NOC (where the community has a developer)
- Drawings and stamped structural calculations
- Photos of the area
Who does what
Step by step
The order can vary by community and authority; we confirm it for your project.
| Step | Approval route | Guides |
|---|---|---|
| Developer NOC Nakheel or wasl | Through the Nakheel online portal or the wasl app. | Nakheel approvals |
| Design Consultant | Drawings and stamped calculations. | — |
| Trakhees submission Consultant | Submission to Trakhees CED, with comments answered. | Trakhees approvals |
| Completion Trakhees | Inspection and completion certificate. | Trakhees completion |
Questions
Related questions
Can I apply to Trakhees myself?
No, submissions must be made by an approved consultant.
Which areas are under Trakhees?
Nakheel communities such as Palm Jumeirah, JVC and Al Furjan, Jumeirah Golf Estates and JAFZA.
Do I need the Nakheel NOC first?
Yes, in Nakheel communities, through the Nakheel online portal.
What is Trakhees CED?
The Civil Engineering Department that approves building works.
What does Structural Solutions do?
We handle the NOC, the Trakhees submission and completion.