7 Smart Steps to Get Trakhees and Nakheel Approval Fast
By Eng Amjed / July 22, 2025
Getting Trakhees and Nakheel approval is essential if you’re planning any villa modification, apartment renovation, or commercial fit-out in Dubai. Whether you’re installing a pergola, expanding your villa, or modifying a retail unit, approvals from these two authorities are non-negotiable. This guide explains the full Nakheel NOC process, Trakhees building permit stages, and everything in between—from villa extension permits to commercial approvals—so your project stays compliant, safe, and stress-free.
Table of Contents
Understanding Trakhees and Nakheel – Who Does What?
🔹 Nakheel – The Master Developer
Nakheel is the master developer responsible for iconic Dubai communities such as:
- Palm Jumeirah
- Jumeirah Village Triangle (JVT)
- Discovery Gardens
- International City
If your property is within a Nakheel-managed area, you must first obtain a Nakheel NOC before applying for any permits.
🔹 Trakhees – The Regulatory Authority
Trakhees is the regulatory arm of the Ports, Customs & Free Zone Corporation (PCFC). It issues:
- Structural approvals
- Fit-out permits
- Safety compliance clearances
- Trakhees building permits after Nakheel NOC
You need Trakhees approval for any construction or modification work—even minor partitions.

7 Smart Steps to Get Trakhees and Nakheel Approval
Step 1: Identify the Scope of Work
Is it a villa modification? An interior partition? A commercial shop fit-out? Clearly define the type of work. Common modification types include:
- Pergola or canopy installation
- Internal partitions
- Kitchen/bathroom renovation
- Room extensions
- Load-bearing wall removal
- Commercial shelving or signage
Step 2: Appoint a Licensed Consultant (or Freelance Engineer)
Approvals require drawings stamped by a Dubai-licensed consultant or qualified structural engineer.
✅ At Structural Solutions, we offer both options:
- Freelance services by S T R SOL DESIGN
- Full consultancy via Nirvana AEC
This gives you flexibility depending on budget and authority requirements.
Step 3: Prepare Technical Drawings
Your consultant must prepare:
- Existing + proposed layout plans
- Structural calculations (if needed)
- Architectural and MEP coordination
- 3D perspectives (for commercial units)
All files must follow Nakheel CAD standards and Trakhees digital submission formats.
Step 4: Apply for Nakheel NOC
Submit your concept plans through the Nakheel Online Portal, attaching:
- Title deed
- Emirates ID
- Contractor appointment letter
- Proposed modification plans
Nakheel may:
- Approve immediately
- Request revisions
- Conduct a site inspection
Typical timeline: 3–10 working days
Step 5: Submit for Trakhees Building Permit
Once Nakheel NOC is issued, your consultant uploads files to Trakhees. Key documents include:
- Approved Nakheel NOC
- Design drawings
- Risk assessments
- Authority forms
- Structural analysis (for load-bearing works)
Permit categories:
- Minor works (partitions, pergolas, landscaping)
- Major works (structural wall changes, new rooms)
Timeline: 5–15 working days
Step 6: Site Works and Inspections
Work can begin only after Trakhees permit is issued. During construction:
- Your engineer may need to supervise
- Trakhees may conduct surprise site visits
- You must maintain site safety standards
Step 7: Completion Certificate or As-Built NOC
Once work is complete, submit:
- Completion report
- As-built drawings
- Contractor completion certificate
Trakhees then closes the file, and Nakheel updates your property record.

Table: Trakhees + Nakheel Approval Documents Checklist
Document | Required For | Who Prepares |
---|---|---|
Title Deed | Nakheel, Trakhees | Owner |
Emirates ID + Passport | Nakheel, Trakhees | Owner |
Consultant Appointment Letter | Both | Owner + Consultant |
Existing and Proposed Layouts | Both | Structural Engineer |
Structural Calculations | Trakhees (if structural) | Engineer |
Risk Assessment / Method Statement | Trakhees | Contractor or Consultant |
As-Built Drawings (at end) | Trakhees | Engineer |
Common Modification Scenarios & Rules
Nakheel Villa Modifications Allowed:
- Pergolas, gazebos, and canopies (with max coverage rules)
- Room extensions within plot boundaries
- Landscaping and BBQ areas
- Boundary wall adjustments
Not Allowed Without Special Approval:
- Modifications beyond setback lines
- Major façade changes
- Rooftop structures
Trakhees Commercial Unit Approvals:
For salons, groceries, cafes, and shops in Nakheel areas:
- Mandatory Trakhees drawings (partition layout, signage, equipment)
- Fire & safety approvals
- Hygiene certificates for food establishments
Key Tips to Speed Up Your Trakhees & Nakheel Approval
- Use a consultant familiar with both portals
- Avoid starting work before the permit is issued
- Get neighbor NOCs for external or shared modifications
- Ensure your contractor is Trakhees-registered
- Work with engineers who understand Trakhees approval requirements
Frequently Asked Questions
Q1: How long does it take to get Trakhees and Nakheel approval?
A: Typically, the process takes 10–25 working days from submission to final permit, depending on project complexity.
Q2: Can I do villa modifications without a consultant?
A: For minor works, a freelance structural engineer might suffice. However, Trakhees often requires a licensed consultancy for structural or commercial modifications.
Q3: What if my villa had old unauthorized changes?
A: You’ll need to apply for a Retrospective NOC through Nakheel, supported by a structural report and as-built drawings approved by Trakhees.
Q4: What’s the difference between Nakheel and Trakhees roles?
A: Nakheel is the master developer issuing the initial NOC; Trakhees is the regulatory authority that reviews engineering, safety, and construction permits.
Q5: Can I modify my shop or office in a Nakheel area?
A: Yes, but you need a Trakhees commercial approval after Nakheel’s consent. This includes fire safety, fit-out drawings, and health approvals if relevant.
Final Call to Action
If you need expert assistance with civil engineering, structural design, or building permit approvals in Dubai, the team at Structural Solutions is ready to help. Contact us on WhatsApp or email us at: info@structuralsolutions.ae We’ll ensure your project meets all Dubai Municipality standards with precision and professionalism.